AI Flow run: codex on board-0
Delivered at 2026-10-13T08:36:35Z: 1912.6 min of AI time from the prompt to "done, here is your video" (8087.4 min on the wall clock). Since then 0.0 min more of AI time over 21 follow-up prompt(s), listed under Sessions; none of it is in the delivery number.
Prompt at 2026-10-07T17:49:14Z (UTC). Flow: board. Every number here is from the run's append-only ledger (run.jsonl). AI time is the time the AI was working on a prompt: from the human's prompt to the AI's done, with any gap over 15 min where no command ran (unobserved, not proven idle) cut out.
The video
The final cut of this run, 274 s: only the moments something moved, every step in order, the AI's analysis drawings fullscreen, the run and step clocks in the corner, the words cut to the picture.
Sessions
One row per human prompt: the AI's time on it, unobserved gaps excluded by the heuristic, which may include external AI work.
| Session | Prompt at | Done at | AI time min | Unobserved gap min | What |
|---|---|---|---|---|---|
| 1 | 2026-10-07T17:49:14Z | (open) | 46.0 | 1019 | the first prompt |
| 2 | 2026-10-08T11:34:31Z | (open) | 9.9 | 114 | User resumed custom electronic load work and reiterated recording clips for a YouTube buil |
| 3 | 2026-10-08T13:38:16Z | (open) | 21.6 | 0 | Continue load design with fan tach and Kelvin-minus probe access; retain two-layer 3rdPart |
| 4 | 2026-10-08T13:59:54Z | (open) | 162.7 | 1037 | Continue through remaining library, cooling, routing and recorded build work |
| 5 | 2026-10-09T09:59:18Z | (open) | 14.4 | 15 | Continue the electronic load through AIFlow to completion, keep dashboard progress visible |
| 6 | 2026-10-09T10:28:54Z | (open) | 13.9 | 35 | Continue electronic-load engineering through AIFlow, with real dashboard progress and clip |
| 7 | 2026-10-09T11:18:03Z | (open) | 4.6 | 69 | Keep going on AIFlow: continue electronic-load engineering and recorded board work. |
| 8 | 2026-10-09T12:31:28Z | (open) | 24.5 | 31 | Resume the electronic load through all AIFlow design gates after dashboard corrections; co |
| 9 | 2026-10-09T13:26:48Z | (open) | 198.1 | 88 | Continue original electronic-load objective. Compact 5 W prototype is the working basis fr |
| 10 | 2026-10-09T18:12:40Z | (open) | 10.1 | 99 | Resume electronic-load completion: inspect native board, land reviewed diode thermal vias |
| 11 | 2026-10-09T20:02:16Z | (open) | 220.9 | 861 | Continue board 18 to completion; resolve package-mounted cooling and thermal solver suppor |
| 12 | 2026-10-10T14:04:14Z | (open) | 202.2 | 312 | Continue electronic-load engineering and recorded workflow; magnetic-field question withdr |
| 13 | 2026-10-10T22:38:10Z | 2026-10-12T02:30:15Z | 689.0 | 983 | Continue to the finish line; resolve supported cooling design and remaining deliverables, |
| 14 | 2026-10-12T02:30:15Z | (open) | 0.0 | 0 | follow-up (no prompt mark; say prompt --text next time) |
| 15 | 2026-10-12T03:31:37Z | (open) | 0.0 | 0 | follow-up (no prompt mark; say prompt --text next time) |
| 16 | 2026-10-12T03:31:37Z | 2026-10-12T04:15:43Z | 44.1 | 0 | keep going then |
| 17 | 2026-10-12T04:15:43Z | (open) | 0.5 | 0 | follow-up (no prompt mark; say prompt --text next time) |
| 18 | 2026-10-12T09:39:32Z | (open) | 0.0 | 0 | follow-up (no prompt mark; say prompt --text next time) |
| 19 | 2026-10-12T09:39:33Z | 2026-10-12T10:08:30Z | 28.9 | 0 | keep going |
| 20 | 2026-10-12T10:08:30Z | (open) | 0.0 | 0 | follow-up (no prompt mark; say prompt --text next time) |
| 21 | 2026-10-12T10:34:04Z | (open) | 0.0 | 0 | follow-up (no prompt mark; say prompt --text next time) |
| 22 | 2026-10-12T10:34:05Z | 2026-10-13T08:36:38Z | 221.1 | 1101 | User confirmed 1 oz finished copper standard, 2 oz on request. Finish board AIFlow design |
| all | 1912.6 |
Per step
AI time only, the idle cut out.
| Step | AI min | AI thinking min | Tool min | Turns | Visits | Returns | Longest think |
|---|---|---|---|---|---|---|---|
| intake | 2.6 | 0.3 | 2.2 | 3 | 1 | 0 | 0.3 min |
| placement | 9.5 | 0.0 | 9.5 | 31 | 5 | 3 | 0.0 min |
| routing | 63.4 | 0.0 | 63.4 | 92 | 7 | 2 | 0.0 min |
| pours | 5.8 | 0.0 | 5.8 | 22 | 3 | 0 | 0.0 min |
| current | 78.5 | 0.0 | 78.5 | 129 | 3 | 0 | 0.0 min |
| thermal | 99.3 | 0.0 | 99.3 | 367 | 3 | 0 | 0.0 min |
| finish | 1.7 | 0.0 | 1.7 | 4 | 2 | 0 | 0.0 min |
| 3d | 2.7 | 0.0 | 2.7 | 7 | 2 | 0 | 0.0 min |
| components | 66.3 | 0.0 | 66.3 | 386 | 2 | 1 | 0.0 min |
| design | 2.5 | 0.0 | 2.5 | 11 | 1 | 0 | 0.0 min |
| export | 0.9 | 0.0 | 0.9 | 10 | 2 | 0 | 0.0 min |
| fields | 13.4 | 0.0 | 13.4 | 9 | 2 | 0 | 0.0 min |
| libraries | 3.8 | 0.0 | 3.8 | 18 | 2 | 0 | 0.0 min |
| models | 15.3 | 0.0 | 15.3 | 30 | 2 | 0 | 0.0 min |
| nets | 1.7 | 0.0 | 1.7 | 4 | 2 | 0 | 0.0 min |
| outline | 1.6 | 0.0 | 1.6 | 10 | 3 | 0 | 0.0 min |
| rules | 1511.1 | 0.0 | 1511.1 | 14 | 1 | 0 | 0.0 min |
| silkscreen | 2.6 | 0.0 | 2.6 | 9 | 2 | 0 | 0.0 min |
| test-plan | 0.7 | 0.0 | 0.7 | 10 | 2 | 0 | 0.0 min |
| thermal-vias | 29.3 | 0.0 | 29.3 | 204 | 6 | 0 | 0.0 min |
| total | 1912.6 | 0.3 | 1912.3 |
Returns to earlier steps
- 2026-10-08T14:37:07Z back to placement (visit 2): Compact BOOST_SW loop and orient precision sense pins toward the shunt before routing
- 2026-10-09T12:52:33Z back to routing (visit 3): Adopt and recheck native USB layout and zero-ohm link revision before remaining thermal and fabrication stages
- 2026-10-09T13:52:38Z back to placement (visit 3): Make room for offset cooling while preserving probe access: relocate TP4, TP8 and fan connector after isolated native zero-error zero-open gate
- 2026-10-09T15:42:59Z back to placement (visit 4): Rotate D1 and reroute power paths after native DRC and paired current review; one shunt constriction remains unresolved
- 2026-10-11T14:37:22Z back to components (visit 2): Component audit is incomplete: 94 pending and 10 stale reference reviews; zero wikiPage links in the register. Reconcile existing reusable pages and create missing qualified part pages before claiming this stage complete. Preserve current PCB and historical analysis evidence.
- 2026-10-13T02:51:38Z back to routing (visit 7): User requested side-fan assembly and completion: apply probing test-pad revisions and revalidate candidate before delivery
Decisions along the way
- 2026-10-07T19:16:59Z clip-start:components-1
- 2026-10-07T19:17:39Z capture-stop
- 2026-10-07T19:19:08Z Native model setup checked; initial placement next
- 2026-10-08T13:45:39Z capture-stop
- 2026-10-08T14:03:26Z clip-start:models-1
- 2026-10-08T14:05:30Z capture-stop
- 2026-10-08T14:06:02Z clip-start:test-plan-1
- 2026-10-08T14:07:02Z clip-start:placement-1
- 2026-10-08T14:10:02Z capture-stop
- 2026-10-08T14:39:33Z clip-start:placement-2
- 2026-10-08T14:41:14Z capture-stop
- 2026-10-08T14:51:51Z capture-stop
- 2026-10-08T20:21:00Z capture-stop
- 2026-10-09T12:54:19Z clip-start:thermal-vias-2
- 2026-10-09T12:55:03Z capture-stop
- 2026-10-09T13:52:39Z clip-start:placement-3
- 2026-10-09T13:53:08Z capture-stop
- 2026-10-09T14:02:23Z capture-start
- 2026-10-09T14:03:16Z capture-stop
- 2026-10-09T14:07:44Z clip-start:routing-4
- 2026-10-09T14:08:29Z clip-start:thermal-vias-3
- 2026-10-09T14:14:53Z capture-stop
- 2026-10-09T14:15:14Z capture-start
- 2026-10-09T14:15:56Z capture-stop
- 2026-10-09T15:43:01Z clip-start:placement-4
- 2026-10-09T15:44:09Z capture-stop
- 2026-10-09T15:46:31Z clip-start:routing-5
- 2026-10-09T15:47:39Z capture-stop
- 2026-10-09T16:06:04Z capture-start
- 2026-10-09T16:07:11Z capture-stop
- 2026-10-09T16:42:14Z artifact analysis-image for thermal-vias-4: Fan component 0.2.1: quiet state cycle and explicit added Adom connector harness. Nominal geometry; physical qualification pending.
- 2026-10-09T18:22:48Z artifact analysis-image for thermal-vias-4: Recorded native landing of nine D1 thermal vias. Saved-board DRC: zero errors and opens; cooling qualification pending.
- 2026-10-09T20:06:14Z artifact analysis-image for thermal-vias-4: Unqualified package-path sensitivity: 5 W, 40 C ambient, unchanged 55 C trip. Ducted flow scenarios are not measured fan performance.
- 2026-10-09T20:13:35Z artifact analysis-image for thermal-vias-4: Unqualified package-cooling sensitivity at 5 W and 40 C ambient; 55 C trip retained. Ducted airflow scenarios are not measured fan performance.
- 2026-10-09T20:25:34Z artifact analysis-image for thermal-vias-4: Board 18 stock-sink envelope candidate. 91 fitted-model boxes and probe circles clear; exact contact, hardware, cradle, plugs and airflow remain unresolved.
- 2026-10-09T20:48:19Z artifact test-report for thermal-vias-4: Output-locked I2C adapter and conversion-age cache: fake-HAL/C tests plus 25 Python tests; physical I2C unverified
- 2026-10-09T20:51:36Z artifact test-report for thermal-vias-4: Nominal ADC conversion tests pass against Vishay table points; MCU build output-locked; calibration and physical acquisition unverified
- 2026-10-09T20:53:47Z artifact test-report for thermal-vias-4: ADC/I2C adapter fault-injection and nominal-conversion host tests pass; output locked, physical operation unverified
- 2026-10-09T23:47:56Z capture-stop
- 2026-10-09T23:49:09Z capture-start
- 2026-10-09T23:52:25Z capture-stop
- 2026-10-09T23:56:27Z clip-start:outline-1
- 2026-10-09T23:56:36Z clip-start:current-1
- 2026-10-09T23:56:59Z capture-stop
- 2026-10-10T13:01:38Z artifact analysis-image for current-1: Candidate v27 native copper review at fine-mesh hotspots; current screen failed, board not landed
- 2026-10-10T15:43:47Z capture-stop
- 2026-10-10T16:16:38Z artifact geometry-review for thermal-1: Exact v85 model reviewed; 1110 valid solids and 11 checked molecule connections; cooling/export contract remains open
- 2026-10-10T16:42:25Z artifact analysis-image for thermal-1: v85 cooling parameter sensitivity: full-power still-air failure retained, no qualification
- 2026-10-10T16:45:23Z artifact thermal-study for thermal-1: Coupled fine-grid package screen and assumptions; formal thermal gate remains open
- 2026-10-10T17:16:55Z artifact review-document for thermal-1: Rotated fan carrier: nominal body/probe clearance; retention and harness unfinished
- 2026-10-10T17:16:55Z artifact review-document for thermal-1: Native two-layer manufacturing review; not fabrication release
- 2026-10-10T17:16:55Z artifact review-video for thermal-1: Actual rotated-carrier inspection at 2x; nominal assembly only
- 2026-10-10T17:17:30Z artifact review-document for thermal-1: Rotated fan carrier: nominal geometry checks; not qualified
- 2026-10-10T17:17:30Z artifact review-document for thermal-1: Review-only native Gerber, drill and position checks
- 2026-10-10T17:32:00Z artifact analysis-image for thermal-1: Single GLB with nominal installed fan harness and simulated states; thermal gate remains open
- 2026-10-10T17:32:00Z artifact review-video for thermal-1: Actual gentle simulated fan state cycle; custom harness study, 2x playback
- 2026-10-10T17:42:05Z artifact analysis-data for thermal-1: Control-panel fan twin verified: disconnected and stale telemetry stay unknown; no hardware measurements
- 2026-10-10T17:54:22Z artifact analysis-data for thermal-1: Insulated sensor candidate: nominal route and bend checks; attachment and calibration unqualified
- 2026-10-10T17:58:29Z artifact analysis-data for thermal-1: Finished copper capability needs confirmation: 17.5 um isolated screen fails five current nets; formal 35 um board unchanged
- 2026-10-10T18:04:06Z artifact engineering-review for thermal-1: 35 µm candidate: six current screens pass; thermal and finished copper unresolved
- 2026-10-10T18:10:21Z artifact engineering-review for thermal-1: PEEK fastener nominal fit; preload, TIM and retention remain unqualified
- 2026-10-10T18:10:41Z artifact engineering-review for thermal-1: PEEK fastener nominal fit; preload, TIM and retention remain unqualified
- 2026-10-10T18:18:11Z artifact engineering-review for thermal-1: Artifact overwrite fix: 150 tests pass; release verification pending
- 2026-10-10T18:20:17Z artifact engineering-review for thermal-1: AIFlow 0.1.87 verified in source, package, download and installation; artifact history protected
- 2026-10-10T18:22:45Z artifact engineering-review for thermal-1: Alternative drawing-led AlN/PEEK stack clears nominal geometry; qualification pending
- 2026-10-10T18:30:03Z artifact engineering-review for thermal-1: 240 host fan-shutdown timing cases pass; hardware latency and thermal qualification remain open
- 2026-10-10T18:32:47Z artifact engineering-review for thermal-1: Passive sink alternatives screened; larger candidate needs mounting and installed-cooling qualification
- 2026-10-10T18:36:42Z artifact procurement-review for thermal-1: Exact-part listings add $6.40; bulk-price and stock exclusions remain explicit
- 2026-10-10T19:44:01Z capture-start
- 2026-10-10T19:44:07Z net DUT_POS: 21 items highlighted
- 2026-10-10T19:44:11Z net DUT_FUSED: 14 items highlighted
- 2026-10-10T19:44:16Z net LOAD_POS: 60 items highlighted
- 2026-10-10T19:44:20Z net SHUNT_P: 23 items highlighted
- 2026-10-10T19:44:25Z net GND: 172 items highlighted
- 2026-10-10T19:44:29Z net 5V_AUX: 77 items highlighted
- 2026-10-10T19:44:42Z capture-stop
- 2026-10-10T19:46:50Z artifact engineering-review for thermal-1: Sensor uncertainty screen: indicated 55 C is not a guaranteed actual-case ceiling
- 2026-10-10T19:48:55Z artifact engineering-review for thermal-1: Actual STM32 fan adapter passes fake-HAL boundary tests; no physical timing claim
- 2026-10-10T22:44:48Z capture-start
- 2026-10-10T22:45:25Z capture-stop
- 2026-10-10T22:48:58Z capture-start
- 2026-10-10T22:49:17Z net USB_DP: 3 items highlighted
- 2026-10-10T22:49:21Z net USB_DM: 6 items highlighted
- 2026-10-10T22:49:26Z net FAN_TACH: 74 items highlighted
- 2026-10-10T22:49:51Z capture-stop
- 2026-10-10T22:58:54Z artifact analysis-image for thermal-1: Board22 exact-file current screen at assumed 35um surface/25um barrel. All six nets below60 A/mm2. Finished copper and thermal qualification remain open.
- 2026-10-10T23:59:36Z artifact analysis-image for thermal-1: Board24 current density: assumed 35/25 µm copper, display capped; exact peak 58.18 A/mm². Thermal qualification open.
- 2026-10-10T23:59:47Z artifact analysis-image for thermal-1: Board24 current density from 16-bit solver textures: assumed 35/25 µm copper; capped display, exact peak 58.18 A/mm². Thermal qualification open.
- 2026-10-11T14:37:38Z capture-stop
- 2026-10-11T17:01:50Z artifact engineering-review for components-2: D1 metadata-only candidate: structural and native DRC checks pass; not adopted
- 2026-10-11T17:03:02Z artifact engineering-review for components-2: Seven IC pin-function reviews against manufacturer documentation; qualification remains open
- 2026-10-11T17:07:53Z artifact engineering-review for components-2: J11 manufacturer hole and project annulus candidate passes native DRC; not yet adopted
- 2026-10-11T17:10:30Z artifact engineering-review for components-2: Q1 larger-hole candidate passes unchanged native DRC rules; formed leads and assembly remain unqualified
- 2026-10-11T17:15:48Z artifact process-video for components-2: Reviewed 2x native candidate orbit; six catalog models and corrected hole variants, qualification open
- 2026-10-11T17:57:05Z artifact video for components-2: Native KiCad inspection of ten marked IC models; 2x excerpt, board26, physical qualification pending
- 2026-10-11T18:16:32Z artifact analysis-image for components-2: Q1 formed-lead study: original nominal CAD, not adopted; mounting and cooling qualification open
- 2026-10-11T18:42:02Z artifact analysis-image for components-2: R7 fault-power candidate: 4.7k Panasonic 0.1W versus existing1k 0.0625W; partial simulation, not hardware qualification.
- 2026-10-11T19:08:37Z artifact process-clip for components-2: Board28 native review after low-voltage Q3/Q4 replacement; 2x actual capture, hardware qualification pending.
- 2026-10-11T19:29:39Z artifact process-clip for components-2: Native Q1 formed-lead detail, 2x actual recording. Nominal geometry only; mounting and thermal qualification remain open.
- 2026-10-11T19:50:16Z artifact video for components-2: Native scaffold-fit candidate: 64x72mm corner span; DRC and nominal XY fit pass, assembly qualification remains open.2x playback.
- 2026-10-11T20:17:57Z artifact video for components-2: JST GH sensor connector candidate: native board overview, 2x playback
- 2026-10-11T20:21:55Z artifact video for components-2: JST GH header: native terminal close-up, 2x playback
- 2026-10-11T23:18:09Z artifact process-video for components-2: Native Board31 land-pattern review, top orbit at2x; prototype, human clip review pending
- 2026-10-12T00:07:22Z artifact process-video for components-2: Native U3/U7 manufacturer-land candidate review, selected excerpt at2x; not physical qualification, recorder timing warning retained
- 2026-10-12T00:09:39Z artifact process-video for components-2: Native U3/U7 candidate overview, corrected exact source1.5–4.5s at2x, duration1.5s; cropped later orbit omitted; capture timing unqualified
- 2026-10-12T00:28:24Z capture-stop
- 2026-10-12T00:33:23Z artifact process-video for libraries-2: MMBT3904 hero repair: live post-publication Wiki viewer review at 2x; top, oblique and underside. Headless browser capture, not original creation footage.
- 2026-10-12T00:36:09Z clip-start:models-2
- 2026-10-12T01:06:48Z artifact analysis-image for models-2: Board32 current screen: six loaded nets pass at assumed 35 µm surface copper. Display clipped; quantitative peaks unclipped. Fabricator and hardware validation pending.
- 2026-10-12T01:08:51Z net GATE: 31 items highlighted
- 2026-10-12T01:08:55Z net SHUNT_P_SENSE: 75 items highlighted
- 2026-10-12T01:09:00Z net FAN_TACH: 74 items highlighted
- 2026-10-12T01:09:18Z capture-stop
- 2026-10-12T01:14:46Z clip-start:placement-5
- 2026-10-12T01:15:29Z capture-stop
- 2026-10-12T01:15:58Z clip-start:routing-6
- 2026-10-12T01:16:49Z clip-start:thermal-vias-5
- 2026-10-12T01:18:22Z clip-start:pours-2
- 2026-10-12T01:19:20Z clip-start:outline-2
- 2026-10-12T01:20:26Z clip-start:current-2
- 2026-10-12T01:20:56Z artifact analysis-image for current-2: Board32 current acceptance: six nets pass at assumed 35 µm surface copper and 25 µm plating. Unclipped peak approximately 58.75 A/mm²; thermal qualification remains open.
- 2026-10-12T01:21:44Z clip-start:thermal-2
- 2026-10-12T01:22:26Z capture-stop
- 2026-10-12T01:25:25Z artifact analysis-image for thermal-2: Board32 supplied-parameter heatsink study: 75.6 C still-air case versus 51.1 C under assumed catalog airflow at 40 C ambient. Thermal gate remains failed; installation and fault timing unqualified.
- 2026-10-12T01:26:14Z artifact analysis-image for thermal-2: Board32 heatsink parameter study: case75.6C still /51.1C assumed forced at40C ambient. PCB hotspot is D1; Q1 has a separate case-to-sink path. Thermal gate remains failed; hardware unqualified.
- 2026-10-12T10:05:58Z artifact process-video for thermal-2: Corrected guard and lifted support: saved-model inspection, nominal geometry only; narration and human editorial review pending
- 2026-10-12T10:57:47Z artifact process-video for thermal-2: Saved-model contact correction: 2.10mm copper spacer and proposed insulated M3x10 attachment. Headless inspection at1x; no physical qualification or final thermal acceptance.
- 2026-10-12T11:11:16Z artifact analysis-image for thermal-2: Formal Board32 supplied-parameter thermal screen. Q1 case52.07C, junction54.38C at40C ambient; unchanged15C hottest-node budget. No fan benefit credited; physical qualification pending.
- 2026-10-12T13:50:11Z net GND: 172 items highlighted
- 2026-10-12T13:50:16Z net SHUNT_P: 23 items highlighted
- 2026-10-12T13:50:20Z net LOAD_POS: 60 items highlighted
- 2026-10-12T13:50:25Z net 5V_AUX: 77 items highlighted
- 2026-10-12T13:50:29Z net DUT_FUSED: 14 items highlighted
- 2026-10-12T13:50:34Z net DUT_POS: 21 items highlighted
- 2026-10-12T13:50:38Z net SHUNT_P_SENSE: 75 items highlighted
- 2026-10-12T13:50:43Z net SHUNT_N_SENSE: 197 items highlighted
- 2026-10-12T13:51:08Z clip-start:silkscreen-1
- 2026-10-12T13:51:28Z capture-stop
- 2026-10-12T13:58:06Z clip-start:3d-1
- 2026-10-12T14:00:57Z clip-start:export-1
- 2026-10-12T14:02:51Z capture-stop
- 2026-10-13T02:51:45Z clip-start:routing-7
- 2026-10-13T02:53:40Z capture-stop
- 2026-10-13T04:16:21Z clip-start:thermal-vias-6
- 2026-10-13T04:16:35Z capture-stop
- 2026-10-13T05:22:06Z clip-start:pours-3
- 2026-10-13T05:22:49Z net GND: 179 items highlighted
- 2026-10-13T05:22:54Z net LOAD_POS: 60 items highlighted
- 2026-10-13T05:22:58Z net SHUNT_P: 23 items highlighted
- 2026-10-13T05:23:56Z clip-start:outline-3
- 2026-10-13T05:28:35Z capture-stop
- 2026-10-13T05:29:54Z clip-start:current-3
- 2026-10-13T05:30:45Z net GND: 179 items highlighted
- 2026-10-13T05:30:50Z net LOAD_POS: 60 items highlighted
- 2026-10-13T05:30:54Z net SHUNT_P: 23 items highlighted
- 2026-10-13T05:31:32Z clip-start:thermal-3
- 2026-10-13T05:33:07Z capture-stop
- 2026-10-13T06:12:36Z artifact probing-collision-review for thermal-3: Board34 R9: full modeled route passes, 20 touches, 14528 poses, zero collisions/snags. Wire wear and thermal qualification remain open.
- 2026-10-13T07:03:17Z artifact analysis-image for thermal-3: Unadopted passive cooling sensitivity. Nominal calculation passes; +10 percent sink resistance fails the unchanged package-rise screen. No installed thermal acceptance.
- 2026-10-13T07:56:41Z artifact analysis-image for fields-2: Board34 / R10 current: fresh 0.1 mm supplied-parameter screen; no hardware qualification
- 2026-10-13T07:56:44Z artifact analysis-image for fields-2: Board34 / R10 heat: fresh 0.1 mm supplied-parameter screen; no hardware qualification
- 2026-10-13T07:56:46Z artifact analysis-image for fields-2: Board34 / R10 temperature: fresh 0.1 mm supplied-parameter screen; no hardware qualification
- 2026-10-13T07:56:52Z clip-start:nets-2
- 2026-10-13T07:57:03Z net GND: 179 items highlighted
- 2026-10-13T07:57:07Z net SHUNT_P: 23 items highlighted
- 2026-10-13T07:57:12Z net LOAD_POS: 60 items highlighted
- 2026-10-13T07:57:16Z net 5V_AUX: 81 items highlighted
- 2026-10-13T07:57:21Z net DUT_FUSED: 14 items highlighted
- 2026-10-13T07:57:25Z net DUT_POS: 21 items highlighted
- 2026-10-13T07:57:29Z net SHUNT_P_SENSE: 86 items highlighted
- 2026-10-13T07:57:34Z net SHUNT_N_SENSE: 197 items highlighted
- 2026-10-13T07:58:14Z clip-start:silkscreen-2
- 2026-10-13T07:59:00Z capture-stop
- 2026-10-13T08:04:25Z clip-start:3d-2
- 2026-10-13T08:06:54Z clip-start:finish-2
- 2026-10-13T08:08:23Z clip-start:export-2
- 2026-10-13T08:08:42Z capture-stop
Where the board stands
- routing: 0 unrouted after null passes
- gate: 0 new DRC errors, 0 unconnected, null inherited
- landed live: 0 of 0 route entries
- pours (verified-existing): 9 groups, failed []
- copper kept (mm2 per layer): {"B.Cu":5808.49,"F.Cu":5530.47}
- analyze-current: pass
- analyze-thermal: pass
The steps on camera
One clip per step visit, sped up 10x, with the editor at the start and the end of the visit. A caption above every clip and screenshot says what it shows.
components
What this step does: Audit wiki component identity, reusable CAD quality and redistribution evidence before placement; offer cached optional MPN-marked variants.
Clip: components, the PCB editor from 2026-10-07T19:16:59Z to 2026-10-07T19:17:39Z. Motion only: 0.6 min of real time, 2 s of it had something moving; the clock in the corner is the real elapsed time.
Contact sheet: nine frames spread through the components clip, what the camera saw.

Screenshot: the board when components began.

libraries
What this step does: Assemble and validate the reviewed symbols, footprints and selected model variants in the chosen EDA before placement.
Clip: libraries, the PCB editor from 2026-10-08T13:45:27Z to 2026-10-08T13:45:39Z. Motion only: 0.2 min of real time, 0 s of it had something moving; the clock in the corner is the real elapsed time.
Contact sheet: nine frames spread through the libraries clip, what the camera saw.

models
What this step does: Check native board model resolution and inspect the selected library variants in the chosen EDA; use the component register for unresolved assets.
Clip: models, the PCB editor from 2026-10-08T14:03:26Z to 2026-10-08T14:05:30Z. Motion only: 2.1 min of real time, 7 s of it had something moving; the clock in the corner is the real elapsed time.
Contact sheet: nine frames spread through the models clip, what the camera saw.

Screenshot: the board when models began.

test-plan
What this step does: Think through how this board will be tested once it is built and on the probing workcell: the measurements a careful engineer would take (rails, switch node, feedback, ripple, enable, LEDs), the net each one needs, and a probe spot for every one. The binary checks each planned measurement has a probe-able spot (a 0.5 mm round test point or an exposed pad the pogo tip can land on, within 50 mm of a ground machine contact, not under a part body) and adds a test point to the netlist for every gap.
Clip: test-plan, the PCB editor from 2026-10-08T14:06:02Z to 2026-10-08T14:06:47Z. Motion only: 0.8 min of real time, 1 s of it had something moving; the clock in the corner is the real elapsed time.
Contact sheet: nine frames spread through the test-plan clip, what the camera saw.

Screenshot: the board when test-plan began.

Screenshot: the board when test-plan ended.

placement
What this step does: place the parts for routability, current and heat; the binary packs, checks courtyards and lands moves; reserve visible space for connector labels and the two-sided service silkscreen; the switch-node check refuses switch copper under another part or a switch loop longer than the spec allows, and sends the AI back here
Clip: placement, the PCB editor from 2026-10-08T14:07:02Z to 2026-10-08T14:10:02Z. Motion only: 3.0 min of real time, 3 s of it had something moving; the clock in the corner is the real elapsed time.
Contact sheet: nine frames spread through the placement clip, what the camera saw.

Screenshot: the board when placement began.

routing
What this step does: route to 100 percent with the spec's rules, gate with KiCad's DRC, land as undo steps; the AI takes it with take route=ai
Clip: routing, the PCB editor from 2026-10-08T14:15:43Z to 2026-10-08T14:37:15Z. Motion only: 21.4 min of real time, 68 s of it had something moving; the clock in the corner is the real elapsed time.
Contact sheet: nine frames spread through the routing clip, what the camera saw.

Screenshot: the board when routing ended.

placement, visit 2 (rework)
What this step does: place the parts for routability, current and heat; the binary packs, checks courtyards and lands moves; reserve visible space for connector labels and the two-sided service silkscreen; the switch-node check refuses switch copper under another part or a switch loop longer than the spec allows, and sends the AI back here
Why the AI came back here: Compact BOOST_SW loop and orient precision sense pins toward the shunt before routing
Clip: placement, visit 2 (rework), the PCB editor from 2026-10-08T14:39:33Z to 2026-10-08T14:41:14Z. Motion only: 1.7 min of real time, 2 s of it had something moving; the clock in the corner is the real elapsed time.
Contact sheet: nine frames spread through the placement, visit 2 (rework) clip, what the camera saw.

Screenshot: the board when placement, visit 2 (rework) began.

routing, visit 2
What this step does: route to 100 percent with the spec's rules, gate with KiCad's DRC, land as undo steps; the AI takes it with take route=ai
Clip: routing, visit 2, the PCB editor from 2026-10-08T14:43:13Z to 2026-10-08T14:51:51Z. Motion only: 8.6 min of real time, 16 s of it had something moving; the clock in the corner is the real elapsed time.
Contact sheet: nine frames spread through the routing, visit 2 clip, what the camera saw.

thermal-vias
What this step does: Heatsink vias where the heat is: for every part that dissipates real power (the regulator, the inductor, the catch diode, the FETs), an array of vias in its thermal pad or the copper it dumps heat into, stitched to the ground or the plane on the other side, sized and counted from its dissipation; the AI reviews the plan and the binary lands it.
Clip: thermal-vias, the PCB editor from 2026-10-08T20:20:41Z to 2026-10-08T20:21:00Z. Motion only: 0.3 min of real time, 0 s of it had something moving; the clock in the corner is the real elapsed time.
Contact sheet: nine frames spread through the thermal-vias clip, what the camera saw.

routing, visit 3 (rework)
What this step does: route to 100 percent with the spec's rules, gate with KiCad's DRC, land as undo steps; the AI takes it with take route=ai
Why the AI came back here: Adopt and recheck native USB layout and zero-ohm link revision before remaining thermal and fabrication stages
Clip: routing, visit 3 (rework), the PCB editor from 2026-10-09T12:52:35Z to 2026-10-09T12:53:57Z. Motion only: 1.4 min of real time, 6 s of it had something moving; the clock in the corner is the real elapsed time.
Contact sheet: nine frames spread through the routing, visit 3 (rework) clip, what the camera saw.

Screenshot: the board when routing, visit 3 (rework) ended.

thermal-vias, visit 2
What this step does: Heatsink vias where the heat is: for every part that dissipates real power (the regulator, the inductor, the catch diode, the FETs), an array of vias in its thermal pad or the copper it dumps heat into, stitched to the ground or the plane on the other side, sized and counted from its dissipation; the AI reviews the plan and the binary lands it.
Clip: thermal-vias, visit 2, the PCB editor from 2026-10-09T12:54:19Z to 2026-10-09T12:55:03Z. Motion only: 0.7 min of real time, 5 s of it had something moving; the clock in the corner is the real elapsed time.
Contact sheet: nine frames spread through the thermal-vias, visit 2 clip, what the camera saw.

Screenshot: the board when thermal-vias, visit 2 began.

placement, visit 3 (rework)
What this step does: place the parts for routability, current and heat; the binary packs, checks courtyards and lands moves; reserve visible space for connector labels and the two-sided service silkscreen; the switch-node check refuses switch copper under another part or a switch loop longer than the spec allows, and sends the AI back here
Why the AI came back here: Make room for offset cooling while preserving probe access: relocate TP4, TP8 and fan connector after isolated native zero-error zero-open gate
Clip: placement, visit 3 (rework), the PCB editor from 2026-10-09T13:52:39Z to 2026-10-09T13:53:08Z. Motion only: 0.5 min of real time, 3 s of it had something moving; the clock in the corner is the real elapsed time.
Contact sheet: nine frames spread through the placement, visit 3 (rework) clip, what the camera saw.

Screenshot: the board when placement, visit 3 (rework) began.

routing, visit 4
What this step does: route to 100 percent with the spec's rules, gate with KiCad's DRC, land as undo steps; the AI takes it with take route=ai
Clip: routing, visit 4, the PCB editor from 2026-10-09T14:07:44Z to 2026-10-09T14:08:19Z. Motion only: 0.6 min of real time, 1 s of it had something moving; the clock in the corner is the real elapsed time.
Contact sheet: nine frames spread through the routing, visit 4 clip, what the camera saw.

Screenshot: the board when routing, visit 4 began.

Screenshot: the board when routing, visit 4 ended.

thermal-vias, visit 3
What this step does: Heatsink vias where the heat is: for every part that dissipates real power (the regulator, the inductor, the catch diode, the FETs), an array of vias in its thermal pad or the copper it dumps heat into, stitched to the ground or the plane on the other side, sized and counted from its dissipation; the AI reviews the plan and the binary lands it.
Clip: thermal-vias, visit 3, the PCB editor from 2026-10-09T14:08:29Z to 2026-10-09T14:14:53Z. Motion only: 6.4 min of real time, 1 s of it had something moving; the clock in the corner is the real elapsed time.
Contact sheet: nine frames spread through the thermal-vias, visit 3 clip, what the camera saw.

Screenshot: the board when thermal-vias, visit 3 began.

placement, visit 4 (rework)
What this step does: place the parts for routability, current and heat; the binary packs, checks courtyards and lands moves; reserve visible space for connector labels and the two-sided service silkscreen; the switch-node check refuses switch copper under another part or a switch loop longer than the spec allows, and sends the AI back here
Why the AI came back here: Rotate D1 and reroute power paths after native DRC and paired current review; one shunt constriction remains unresolved
Clip: placement, visit 4 (rework), the PCB editor from 2026-10-09T15:43:01Z to 2026-10-09T15:44:09Z. Motion only: 1.1 min of real time, 12 s of it had something moving; the clock in the corner is the real elapsed time.
Contact sheet: nine frames spread through the placement, visit 4 (rework) clip, what the camera saw.

Screenshot: the board when placement, visit 4 (rework) began.

routing, visit 5
What this step does: route to 100 percent with the spec's rules, gate with KiCad's DRC, land as undo steps; the AI takes it with take route=ai
Clip: routing, visit 5, the PCB editor from 2026-10-09T15:46:31Z to 2026-10-09T15:47:39Z. Motion only: 1.1 min of real time, 1 s of it had something moving; the clock in the corner is the real elapsed time.
Contact sheet: nine frames spread through the routing, visit 5 clip, what the camera saw.

Screenshot: the board when routing, visit 5 began.

pours
What this step does: pour every net the spec names, keepouts along Kelvin taps, thermal and stitching vias, land, measure the copper kept
Clip: pours, the PCB editor from 2026-10-09T23:46:53Z to 2026-10-09T23:47:56Z. Motion only: 1.0 min of real time, 4 s of it had something moving; the clock in the corner is the real elapsed time.
Contact sheet: nine frames spread through the pours clip, what the camera saw.

outline
What this step does: Round the board's corners: every sharp outline corner becomes a radius (1.0 mm by default, spec outline.cornerRadius), so the board is kind to hands, panels and the fab's router.
Clip: outline, the PCB editor from 2026-10-09T23:56:27Z to 2026-10-09T23:56:30Z. Motion only: 0.1 min of real time, 1 s of it had something moving; the clock in the corner is the real elapsed time.
Contact sheet: nine frames spread through the outline clip, what the camera saw.

Screenshot: the board when outline began.

Screenshot: the board when outline ended.

current
What this step does: IPC-2221 on every loaded net, pour and via capacity, the same-layer rule; then the AI's own current density drawing and a walkthrough of the pours it judged
Clip: current, the PCB editor from 2026-10-09T23:56:36Z to 2026-10-09T23:56:59Z. Motion only: 0.4 min of real time, 1 s of it had something moving; the clock in the corner is the real elapsed time.
Contact sheet: nine frames spread through the current clip, what the camera saw.

Screenshot: the board when current began.

The AI's drawing: Candidate v27 native copper review at fine-mesh hotspots; current screen failed, board not landed

thermal
What this step does: copper and vias at every hot tab against the rise budget; then the AI's own temperature rise drawing and a walkthrough of the pours it judged
Clip: thermal, the PCB editor from 2026-10-10T15:43:32Z to 2026-10-10T15:43:47Z. Motion only: 0.3 min of real time, 1 s of it had something moving; the clock in the corner is the real elapsed time.
Contact sheet: nine frames spread through the thermal clip, what the camera saw.

The AI's file: Exact v85 model reviewed; 1110 valid solids and 11 checked molecule connections; cooling/export contract remains open thermal-1-geometry-review-0.md
The AI's drawing: v85 cooling parameter sensitivity: full-power still-air failure retained, no qualification

The AI's file: Coupled fine-grid package screen and assumptions; formal thermal gate remains open thermal-1-thermal-study-2.md
The AI's file: Actual rotated-carrier inspection at 2x; nominal assembly only thermal-1-review-video-3.mp4
The AI's file: Rotated fan carrier: nominal geometry checks; not qualified thermal-1-review-document-4.json
The AI's file: Review-only native Gerber, drill and position checks thermal-1-review-document-5.json
The AI's drawing: Single GLB with nominal installed fan harness and simulated states; thermal gate remains open

The AI's file: Actual gentle simulated fan state cycle; custom harness study, 2x playback thermal-1-review-video-7.mp4
The AI's file: Control-panel fan twin verified: disconnected and stale telemetry stay unknown; no hardware measurements thermal-1-analysis-data-8.json
The AI's file: Insulated sensor candidate: nominal route and bend checks; attachment and calibration unqualified thermal-1-analysis-data-9.json
The AI's file: Finished copper capability needs confirmation: 17.5 um isolated screen fails five current nets; formal 35 um board unchanged thermal-1-analysis-data-10.json
The AI's file: 35 µm candidate: six current screens pass; thermal and finished copper unresolved thermal-1-engineering-review-11.json
The AI's file: PEEK fastener nominal fit; preload, TIM and retention remain unqualified thermal-1-engineering-review-12.json
The AI's file: AIFlow 0.1.87 verified in source, package, download and installation; artifact history protected thermal-1-engineering-review-13.json
The AI's file: Alternative drawing-led AlN/PEEK stack clears nominal geometry; qualification pending thermal-1-engineering-review-14.json
The AI's file: 240 host fan-shutdown timing cases pass; hardware latency and thermal qualification remain open thermal-1-engineering-review-15.json
The AI's file: Passive sink alternatives screened; larger candidate needs mounting and installed-cooling qualification thermal-1-engineering-review-16.json
The AI's file: Exact-part listings add $6.40; bulk-price and stock exclusions remain explicit thermal-1-procurement-review-17.json
The AI's file: Sensor uncertainty screen: indicated 55 C is not a guaranteed actual-case ceiling thermal-1-engineering-review-18.json
The AI's file: Actual STM32 fan adapter passes fake-HAL boundary tests; no physical timing claim thermal-1-engineering-review-19.json
The AI's drawing: Board22 exact-file current screen at assumed 35um surface/25um barrel. All six nets below60 A/mm2. Finished copper and thermal qualification remain open.

The AI's drawing: Board24 current density from 16-bit solver textures: assumed 35/25 µm copper; capped display, exact peak 58.18 A/mm². Thermal qualification open.

components, visit 2 (rework)
What this step does: Audit wiki component identity, reusable CAD quality and redistribution evidence before placement; offer cached optional MPN-marked variants.
Why the AI came back here: Component audit is incomplete: 94 pending and 10 stale reference reviews; zero wikiPage links in the register. Reconcile existing reusable pages and create missing qualified part pages before claiming this stage complete. Preserve current PCB and historical analysis evidence.
This clip filmed nothing usable: 8 of 8 sampled frames are one flat colour in the middle of the window (an unpainted or covered canvas). It is kept as evidence and left out of the video.
Clip: components, visit 2 (rework), the PCB editor from 2026-10-11T14:37:27Z to 2026-10-11T14:37:38Z. Motion only: 0.2 min of real time, 0 s of it had something moving; the clock in the corner is the real elapsed time.
Contact sheet: nine frames spread through the components, visit 2 (rework) clip, what the camera saw.

The AI's file: D1 metadata-only candidate: structural and native DRC checks pass; not adopted components-2-engineering-review-0.json
The AI's file: Seven IC pin-function reviews against manufacturer documentation; qualification remains open components-2-engineering-review-1.json
The AI's file: J11 manufacturer hole and project annulus candidate passes native DRC; not yet adopted components-2-engineering-review-2.json
The AI's file: Q1 larger-hole candidate passes unchanged native DRC rules; formed leads and assembly remain unqualified components-2-engineering-review-3.json
The AI's file: Reviewed 2x native candidate orbit; six catalog models and corrected hole variants, qualification open components-2-process-video-4.mp4
The AI's file: Native KiCad inspection of ten marked IC models; 2x excerpt, board26, physical qualification pending components-2-video-5.mp4
The AI's drawing: Q1 formed-lead study: original nominal CAD, not adopted; mounting and cooling qualification open

The AI's drawing: R7 fault-power candidate: 4.7k Panasonic 0.1W versus existing1k 0.0625W; partial simulation, not hardware qualification.

The AI's file: Board28 native review after low-voltage Q3/Q4 replacement; 2x actual capture, hardware qualification pending. components-2-process-clip-8.mp4
The AI's file: Native Q1 formed-lead detail, 2x actual recording. Nominal geometry only; mounting and thermal qualification remain open. components-2-process-clip-9.mp4
The AI's file: Native scaffold-fit candidate: 64x72mm corner span; DRC and nominal XY fit pass, assembly qualification remains open.2x playback. components-2-video-10.mp4
The AI's file: JST GH sensor connector candidate: native board overview, 2x playback components-2-video-11.mp4
The AI's file: JST GH header: native terminal close-up, 2x playback components-2-video-12.mp4
The AI's file: Native Board31 land-pattern review, top orbit at2x; prototype, human clip review pending components-2-process-video-13.mp4
The AI's file: Native U3/U7 candidate overview, corrected exact source1.5–4.5s at2x, duration1.5s; cropped later orbit omitted; capture timing unqualified components-2-process-video-14.mp4
libraries, visit 2
What this step does: Assemble and validate the reviewed symbols, footprints and selected model variants in the chosen EDA before placement.
Why the AI came back here: Continue exact-part library acceptance and canonical component hero repairs for adopted Board32
Clip: libraries, visit 2, the PCB editor from 2026-10-12T00:28:08Z to 2026-10-12T00:28:24Z. Motion only: 0.3 min of real time, 3 s of it had something moving; the clock in the corner is the real elapsed time.
Contact sheet: nine frames spread through the libraries, visit 2 clip, what the camera saw.

The AI's file: MMBT3904 hero repair: live post-publication Wiki viewer review at 2x; top, oblique and underside. Headless browser capture, not original creation footage. libraries-2-process-video-0.mp4
models, visit 2
What this step does: Check native board model resolution and inspect the selected library variants in the chosen EDA; use the component register for unresolved assets.
Clip: models, visit 2, the PCB editor from 2026-10-12T00:36:29Z to 2026-10-12T00:36:54Z. Motion only: 0.4 min of real time, 10 s of it had something moving; the clock in the corner is the real elapsed time.
Contact sheet: nine frames spread through the models, visit 2 clip, what the camera saw.

Screenshot: the board when models, visit 2 began.

test-plan, visit 2
What this step does: Think through how this board will be tested once it is built and on the probing workcell: the measurements a careful engineer would take (rails, switch node, feedback, ripple, enable, LEDs), the net each one needs, and a probe spot for every one. The binary checks each planned measurement has a probe-able spot (a 0.5 mm round test point or an exposed pad the pogo tip can land on, within 50 mm of a ground machine contact, not under a part body) and adds a test point to the netlist for every gap.
Why the AI came back here: Fresh Board32 model checks complete; revalidate all nine probe measurements and record key test nets
Clip: test-plan, visit 2, the PCB editor from 2026-10-12T01:08:28Z to 2026-10-12T01:09:18Z. Motion only: 0.8 min of real time, 2 s of it had something moving; the clock in the corner is the real elapsed time.
Contact sheet: nine frames spread through the test-plan, visit 2 clip, what the camera saw.

placement, visit 5
What this step does: place the parts for routability, current and heat; the binary packs, checks courtyards and lands moves; reserve visible space for connector labels and the two-sided service silkscreen; the switch-node check refuses switch copper under another part or a switch loop longer than the spec allows, and sends the AI back here
Why the AI came back here: Verify adopted Board32 poses and native placement constraints without replaying moves
Clip: placement, visit 5, the PCB editor from 2026-10-12T01:14:46Z to 2026-10-12T01:15:29Z. Motion only: 0.7 min of real time, 0 s of it had something moving; the clock in the corner is the real elapsed time.
Contact sheet: nine frames spread through the placement, visit 5 clip, what the camera saw.

Screenshot: the board when placement, visit 5 began.

routing, visit 6
What this step does: route to 100 percent with the spec's rules, gate with KiCad's DRC, land as undo steps; the AI takes it with take route=ai
Why the AI came back here: Adopted Board32 copper is already routed; verify existing routing and retain it
Clip: routing, visit 6, the PCB editor from 2026-10-12T01:15:58Z to 2026-10-12T01:16:41Z. Motion only: 0.7 min of real time, 0 s of it had something moving; the clock in the corner is the real elapsed time.
Contact sheet: nine frames spread through the routing, visit 6 clip, what the camera saw.

Screenshot: the board when routing, visit 6 began.

Screenshot: the board when routing, visit 6 ended.

thermal-vias, visit 5
What this step does: Heatsink vias where the heat is: for every part that dissipates real power (the regulator, the inductor, the catch diode, the FETs), an array of vias in its thermal pad or the copper it dumps heat into, stitched to the ground or the plane on the other side, sized and counted from its dissipation; the AI reviews the plan and the binary lands it.
Why the AI came back here: Existing routing retained; check local thermal paths without claiming heatsink qualification
Clip: thermal-vias, visit 5, the PCB editor from 2026-10-12T01:16:49Z to 2026-10-12T01:18:12Z. Motion only: 1.4 min of real time, 0 s of it had something moving; the clock in the corner is the real elapsed time.
Contact sheet: nine frames spread through the thermal-vias, visit 5 clip, what the camera saw.

Screenshot: the board when thermal-vias, visit 5 began.

Screenshot: the board when thermal-vias, visit 5 ended.

pours, visit 2
What this step does: pour every net the spec names, keepouts along Kelvin taps, thermal and stitching vias, land, measure the copper kept
Why the AI came back here: Board32 via-count review retains seven D1 and three shunt vias; Q1 direct heatsink qualification remains open
Clip: pours, visit 2, the PCB editor from 2026-10-12T01:18:22Z to 2026-10-12T01:19:11Z. Motion only: 0.8 min of real time, 0 s of it had something moving; the clock in the corner is the real elapsed time.
Contact sheet: nine frames spread through the pours, visit 2 clip, what the camera saw.

Screenshot: the board when pours, visit 2 began.

Screenshot: the board when pours, visit 2 ended.

outline, visit 2
What this step does: Round the board's corners: every sharp outline corner becomes a radius (1.0 mm by default, spec outline.cornerRadius), so the board is kind to hands, panels and the fab's router.
Why the AI came back here: Existing saved pours match reviewed polygons/settings; check adopted rounded outline
Clip: outline, visit 2, the PCB editor from 2026-10-12T01:19:20Z to 2026-10-12T01:20:17Z. Motion only: 0.9 min of real time, 0 s of it had something moving; the clock in the corner is the real elapsed time.
Contact sheet: nine frames spread through the outline, visit 2 clip, what the camera saw.

Screenshot: the board when outline, visit 2 began.

Screenshot: the board when outline, visit 2 ended.

current, visit 2
What this step does: IPC-2221 on every loaded net, pour and via capacity, the same-layer rule; then the AI's own current density drawing and a walkthrough of the pours it judged
Why the AI came back here: Saved pours verified and rounded outline retained; record fresh same-input current acceptance
Clip: current, visit 2, the PCB editor from 2026-10-12T01:20:26Z to 2026-10-12T01:21:35Z. Motion only: 1.1 min of real time, 0 s of it had something moving; the clock in the corner is the real elapsed time.
Contact sheet: nine frames spread through the current, visit 2 clip, what the camera saw.

Screenshot: the board when current, visit 2 began.

Screenshot: the board when current, visit 2 ended.

The AI's drawing: Board32 current acceptance: six nets pass at assumed 35 µm surface copper and 25 µm plating. Unclipped peak approximately 58.75 A/mm²; thermal qualification remains open.

thermal, visit 2
What this step does: copper and vias at every hot tab against the rise budget; then the AI's own temperature rise drawing and a walkthrough of the pours it judged
Why the AI came back here: Current screen passes on Board32; retain full heat and case ceiling while reviewing physical cooling interface
Clip: thermal, visit 2, the PCB editor from 2026-10-12T01:21:44Z to 2026-10-12T01:22:26Z. Motion only: 0.7 min of real time, 0 s of it had something moving; the clock in the corner is the real elapsed time.
Contact sheet: nine frames spread through the thermal, visit 2 clip, what the camera saw.

Screenshot: the board when thermal, visit 2 began.

The AI's drawing: Board32 heatsink parameter study: case75.6C still /51.1C assumed forced at40C ambient. PCB hotspot is D1; Q1 has a separate case-to-sink path. Thermal gate remains failed; hardware unqualified.

The AI's file: Corrected guard and lifted support: saved-model inspection, nominal geometry only; narration and human editorial review pending thermal-2-process-video-1.mp4
The AI's file: Saved-model contact correction: 2.10mm copper spacer and proposed insulated M3x10 attachment. Headless inspection at1x; no physical qualification or final thermal acceptance. thermal-2-process-video-2.mp4
The AI's drawing: Formal Board32 supplied-parameter thermal screen. Q1 case52.07C, junction54.38C at40C ambient; unchanged15C hottest-node budget. No fan benefit credited; physical qualification pending.

fields
What this step does: the fields on the board: adom-fields solves the current density of every loaded net, the heat flow in each copper layer with the vias, and the temperature over the board; the AI reads the issues and walks the board in the app on camera
Clip: fields, the PCB editor from 2026-10-12T13:42:33Z to 2026-10-12T13:47:27Z. Motion only: 4.7 min of real time, 200 s of it had something moving; the clock in the corner is the real elapsed time.
Contact sheet: nine frames spread through the fields clip, what the camera saw.

nets
What this step does: the copper pour walkthrough: every poured net (and every loaded, wide or Kelvin net) highlighted on its own in turn, the board framed, so the viewer sees where each net's copper is; the AI names each one
Clip: nets, the PCB editor from 2026-10-12T13:49:46Z to 2026-10-12T13:50:55Z. Motion only: 1.1 min of real time, 16 s of it had something moving; the clock in the corner is the real elapsed time.
Contact sheet: nine frames spread through the nets clip, what the camera saw.

Screenshot: the board when nets ended.

silkscreen
What this step does: Make both faces useful in real service: references and values, verified connector and machine-contact pinouts, polarity, board identity and bring-up labels; review native plots and assembled visibility. Offer the optional shared silkscreen dashboard: real solver events, candidate reasons, live/replay separation, fitted-model inspection and separately recorded detailed/5s replays. Audit every fitted body and every via/hole across the whole board, both faces, with coverage counts. Missing Fab geometry is not free space; native DRC does not establish fitted visibility. Keep unresolved labels explicit and do not apply an incomplete layout. Native geometry/edit/undo/refresh belongs to the EDA bridge.
Clip: silkscreen, the PCB editor from 2026-10-12T13:51:08Z to 2026-10-12T13:51:28Z. Motion only: 0.3 min of real time, 2 s of it had something moving; the clock in the corner is the real elapsed time.
Contact sheet: nine frames spread through the silkscreen clip, what the camera saw.

Screenshot: the board when silkscreen began.

3d
What this step does: the 3D walkthrough: the viewer opened from the editor, then fit, top, tilt, orbit, zoom in, swing, front, bottom, flip, top, fit, all by menu command, no mouse
Clip: 3d, the PCB editor from 2026-10-12T13:58:38Z to 2026-10-12T13:59:03Z. Motion only: 0.4 min of real time, 9 s of it had something moving; the clock in the corner is the real elapsed time.
Contact sheet: nine frames spread through the 3d clip, what the camera saw.

Screenshot: the board when 3d began.

finish
What this step does: finish refuses until everything is true; the AI cuts the video and delivers
Clip: finish, the PCB editor from 2026-10-12T13:59:30Z to 2026-10-12T14:00:06Z. Motion only: 0.6 min of real time, 5 s of it had something moving; the clock in the corner is the real elapsed time.
Contact sheet: nine frames spread through the finish clip, what the camera saw.

export
What this step does: The finish line for the human: Gerbers, drill, BOM and pick-and-place (CPL) written from the finished board, checked, and announced in the chat with where every file is.
Clip: export, the PCB editor from 2026-10-12T14:00:57Z to 2026-10-12T14:02:51Z. Motion only: 1.9 min of real time, 6 s of it had something moving; the clock in the corner is the real elapsed time.
Contact sheet: nine frames spread through the export clip, what the camera saw.

Screenshot: the board when export began.

routing, visit 7 (rework)
What this step does: route to 100 percent with the spec's rules, gate with KiCad's DRC, land as undo steps; the AI takes it with take route=ai
Why the AI came back here: User requested side-fan assembly and completion: apply probing test-pad revisions and revalidate candidate before delivery
Clip: routing, visit 7 (rework), the PCB editor from 2026-10-13T02:51:45Z to 2026-10-13T02:53:40Z. Motion only: 1.9 min of real time, 3 s of it had something moving; the clock in the corner is the real elapsed time.
Contact sheet: nine frames spread through the routing, visit 7 (rework) clip, what the camera saw.

Screenshot: the board when routing, visit 7 (rework) began.

thermal-vias, visit 6
What this step does: Heatsink vias where the heat is: for every part that dissipates real power (the regulator, the inductor, the catch diode, the FETs), an array of vias in its thermal pad or the copper it dumps heat into, stitched to the ground or the plane on the other side, sized and counted from its dissipation; the AI reviews the plan and the binary lands it.
Clip: thermal-vias, visit 6, the PCB editor from 2026-10-13T04:16:21Z to 2026-10-13T04:16:35Z. Motion only: 0.2 min of real time, 0 s of it had something moving; the clock in the corner is the real elapsed time.
Contact sheet: nine frames spread through the thermal-vias, visit 6 clip, what the camera saw.

Screenshot: the board when thermal-vias, visit 6 began.

pours, visit 3
What this step does: pour every net the spec names, keepouts along Kelvin taps, thermal and stitching vias, land, measure the copper kept
Why the AI came back here: Board34 local via-count review complete; reverify existing saved pours against exact current specification
Clip: pours, visit 3, the PCB editor from 2026-10-13T05:22:06Z to 2026-10-13T05:23:36Z. Motion only: 1.5 min of real time, 4 s of it had something moving; the clock in the corner is the real elapsed time.
Contact sheet: nine frames spread through the pours, visit 3 clip, what the camera saw.

Screenshot: the board when pours, visit 3 began.

Screenshot: the board when pours, visit 3 ended.

outline, visit 3
What this step does: Round the board's corners: every sharp outline corner becomes a radius (1.0 mm by default, spec outline.cornerRadius), so the board is kind to hands, panels and the fab's router.
Why the AI came back here: Existing Board34 pours verified and copper measured; check current rounded outline
Clip: outline, visit 3, the PCB editor from 2026-10-13T05:23:56Z to 2026-10-13T05:28:35Z. Motion only: 4.6 min of real time, 0 s of it had something moving; the clock in the corner is the real elapsed time.
Contact sheet: nine frames spread through the outline, visit 3 clip, what the camera saw.

Screenshot: the board when outline, visit 3 began.

current, visit 3
What this step does: IPC-2221 on every loaded net, pour and via capacity, the same-layer rule; then the AI's own current density drawing and a walkthrough of the pours it judged
Why the AI came back here: Verified existing rounded Board34 outline; zero geometry changes.
Clip: current, visit 3, the PCB editor from 2026-10-13T05:29:54Z to 2026-10-13T05:31:15Z. Motion only: 1.3 min of real time, 3 s of it had something moving; the clock in the corner is the real elapsed time.
Contact sheet: nine frames spread through the current, visit 3 clip, what the camera saw.

Screenshot: the board when current, visit 3 began.

Screenshot: the board when current, visit 3 ended.

thermal, visit 3
What this step does: copper and vias at every hot tab against the rise budget; then the AI's own temperature rise drawing and a walkthrough of the pours it judged
Why the AI came back here: Board34 exact-spec current screen and native net walkthrough passed; cooling assembly acceptance remains open.
Clip: thermal, visit 3, the PCB editor from 2026-10-13T05:31:32Z to 2026-10-13T05:33:07Z. Motion only: 1.6 min of real time, 0 s of it had something moving; the clock in the corner is the real elapsed time.
Contact sheet: nine frames spread through the thermal, visit 3 clip, what the camera saw.

Screenshot: the board when thermal, visit 3 began.

The AI's file: Board34 R9: full modeled route passes, 20 touches, 14528 poses, zero collisions/snags. Wire wear and thermal qualification remain open. thermal-3-probing-collision-review-0.json
The AI's drawing: Unadopted passive cooling sensitivity. Nominal calculation passes; +10 percent sink resistance fails the unchanged package-rise screen. No installed thermal acceptance.

fields, visit 2
What this step does: the fields on the board: adom-fields solves the current density of every loaded net, the heat flow in each copper layer with the vias, and the temperature over the board; the AI reads the issues and walks the board in the app on camera
Clip: fields, visit 2, the PCB editor from 2026-10-13T07:50:13Z to 2026-10-13T07:54:58Z. Motion only: 4.7 min of real time, 174 s of it had something moving; the clock in the corner is the real elapsed time.
Contact sheet: nine frames spread through the fields, visit 2 clip, what the camera saw.

The AI's drawing: Board34 / R10 current: fresh 0.1 mm supplied-parameter screen; no hardware qualification

The AI's drawing: Board34 / R10 heat: fresh 0.1 mm supplied-parameter screen; no hardware qualification

The AI's drawing: Board34 / R10 temperature: fresh 0.1 mm supplied-parameter screen; no hardware qualification

nets, visit 2
What this step does: the copper pour walkthrough: every poured net (and every loaded, wide or Kelvin net) highlighted on its own in turn, the board framed, so the viewer sees where each net's copper is; the AI names each one
Clip: nets, visit 2, the PCB editor from 2026-10-13T07:56:52Z to 2026-10-13T07:58:03Z. Motion only: 1.2 min of real time, 5 s of it had something moving; the clock in the corner is the real elapsed time.
Contact sheet: nine frames spread through the nets, visit 2 clip, what the camera saw.

Screenshot: the board when nets, visit 2 began.

Screenshot: the board when nets, visit 2 ended.

silkscreen, visit 2
What this step does: Make both faces useful in real service: references and values, verified connector and machine-contact pinouts, polarity, board identity and bring-up labels; review native plots and assembled visibility. Offer the optional shared silkscreen dashboard: real solver events, candidate reasons, live/replay separation, fitted-model inspection and separately recorded detailed/5s replays. Audit every fitted body and every via/hole across the whole board, both faces, with coverage counts. Missing Fab geometry is not free space; native DRC does not establish fitted visibility. Keep unresolved labels explicit and do not apply an incomplete layout. Native geometry/edit/undo/refresh belongs to the EDA bridge.
Clip: silkscreen, visit 2, the PCB editor from 2026-10-13T07:58:14Z to 2026-10-13T07:59:00Z. Motion only: 0.4 min of real time, 10 s of it had something moving; the clock in the corner is the real elapsed time.
Contact sheet: nine frames spread through the silkscreen, visit 2 clip, what the camera saw.

Screenshot: the board when silkscreen, visit 2 began.

silkscreen, visit 2
What this step does: Make both faces useful in real service: references and values, verified connector and machine-contact pinouts, polarity, board identity and bring-up labels; review native plots and assembled visibility. Offer the optional shared silkscreen dashboard: real solver events, candidate reasons, live/replay separation, fitted-model inspection and separately recorded detailed/5s replays. Audit every fitted body and every via/hole across the whole board, both faces, with coverage counts. Missing Fab geometry is not free space; native DRC does not establish fitted visibility. Keep unresolved labels explicit and do not apply an incomplete layout. Native geometry/edit/undo/refresh belongs to the EDA bridge.
Clip: silkscreen, visit 2, the PCB editor from 2026-10-13T08:01:11Z to 2026-10-13T08:01:36Z. Motion only: 0.4 min of real time, 10 s of it had something moving; the clock in the corner is the real elapsed time.
Contact sheet: nine frames spread through the silkscreen, visit 2 clip, what the camera saw.

Screenshot: the board when silkscreen, visit 2 began.

3d, visit 2
What this step does: the 3D walkthrough: the viewer opened from the editor, then fit, top, tilt, orbit, zoom in, swing, front, bottom, flip, top, fit, all by menu command, no mouse
Clip: 3d, visit 2, the PCB editor from 2026-10-13T08:05:20Z to 2026-10-13T08:05:45Z. Motion only: 0.4 min of real time, 10 s of it had something moving; the clock in the corner is the real elapsed time.
Contact sheet: nine frames spread through the 3d, visit 2 clip, what the camera saw.

Screenshot: the board when 3d, visit 2 began.

finish, visit 2
What this step does: finish refuses until everything is true; the AI cuts the video and delivers
Clip: finish, visit 2, the PCB editor from 2026-10-13T08:06:54Z to 2026-10-13T08:07:43Z. Motion only: 0.8 min of real time, 0 s of it had something moving; the clock in the corner is the real elapsed time.
Contact sheet: nine frames spread through the finish, visit 2 clip, what the camera saw.

Screenshot: the board when finish, visit 2 began.

export, visit 2
What this step does: The finish line for the human: Gerbers, drill, BOM and pick-and-place (CPL) written from the finished board, checked, and announced in the chat with where every file is.
Clip: export, visit 2, the PCB editor from 2026-10-13T08:08:23Z to 2026-10-13T08:08:42Z. Motion only: 0.3 min of real time, 0 s of it had something moving; the clock in the corner is the real elapsed time.
Contact sheet: nine frames spread through the export, visit 2 clip, what the camera saw.

Screenshot: the board when export, visit 2 began.

Delivered
What the AI said when it delivered (the video is at the top of this page):
Board34/R10 prototype design finish passed with unchanged limits and nominal passive cooling assumptions. Exact full probing replay and native export checks pass. Updated Wiki and 4m34s narrated review cut are delivered for editorial review; physical qualification, purchasing, flashing and YouTube publication remain separate. The historical flat components take window-532768-20261011-143726.mp4 is excluded from the selected edit; its suspect flag is preserved.
Plan usage, the second cost line
Percent of each plan limit used, as the provider reports it, at the start of the run and at its end.
| Provider | Limit | At start | At end | Used by this run |
|---|---|---|---|---|
| claude | 5h | 17 % | 9 % | -8.0 % |
| claude | Fable | 0 % | 0 % | 0.0 % |
| claude | week | 54 % | 27 % | -27.0 % |
| codex | week | 2 % | 9 % | 7.0 % |
The limits are per account, not per run: every AI thread signed in as this user draws on the same numbers, so a run made while other threads were working shows their usage too. Read it as an upper bound unless this run was the only thread active.
Given back
7 issue(s) or PR(s) filed by this run's AI to make the tool better for every Adom user:
- pr https://wiki.adom.inc/adom/adom-aiflow/prs/32: Browser access classifier and required off-board component wiki coverage; tested candidate, awaiting owner merge and release
- issue https://wiki.adom.inc/adom/adom-aiflow/issues/40: Stale pour plan hid diode cooling-via candidates after a native zone relocation; request input freshness checks.
- issue https://wiki.adom.inc/adom/component-hero/issues/1: Mechanical-only fan mounting footprint has no copper pads; generator needs a genuine mechanical hero path.
- pr https://wiki.adom.inc/adom/adom-fields/prs/9: Distributed plated-wall coupling and removed drill voids; 32 tests; stacked owner review, shared runtime unchanged
- issue https://wiki.adom.inc/adom/adom-step2glb/issues/25: Generic duplicate molecule contact names and unverified symbol/marker contract; raw evidence and checked local derivatives supplied
- pr https://wiki.adom.inc/adom/adom-fields/prs/11: Package-to-sink thermal nodes, no double heating, physical-pad links, conservative screening; 20 tests and release build pass; owner review pending
- issue https://wiki.adom.inc/adom/service-kicad/issues/9: Native directory export transfer and premature cleanup defect; named-folder individual-file recovery verified
Adom processes PRs within minutes during business hours: a non-stop PR intake runs all day.