e2348d8
Completion plan: compact R11
Active run: aiflow/compact-r11. User authorized implementation and process recording on 13 October 2026. Board34/R10 remains the archived electrical baseline in aiflow/run; its gates do not qualify this revision.
Required work
- Record scope and preserve baseline identity:
revisions/compact-r11/requirements.json. - Source exact commercial approximately 40 mm tall-fin sink and documented PWM/tach fan, including drawings and connector.
- Design an assumption-based insulated Q1 clamp, sensor retention, carrier and duct; manufactured fit, strength and airflow remain unqualified.
- Pack and route 72 x 72 mm target, large pins at 64 mm spacing, edge USB-C, two-layer 1 oz 3rdPartyFab rules. Retain Q1 and D1.
- Revalidate netlist, libraries, models, DRC, current and Q1/PCB thermal paths with fan-on/off boundaries.
- Complete assembled probe simulation including all existing measurements, fan wiring and cooler.
- Compile and bench-simulate output-locked PWM/fault firmware (hardware qualification remains open); retain 5 W cap, output lock and existing temperature protections.
- Write physical cooler/clamp fixture procedure. Physical measurements are pending hardware and cannot be fabricated.
- Publish the prototype board, assumed assembly, R11 specification, review evidence and exact qualification status.
- Publish the approved six-scene chapter in a 4:09 narrated film with selectable captions. New assembly iteration clips remain separate and unapproved.
Scope boundaries
72 x 72 mm is a fit target, not an accepted layout. No higher wattage rating, temperature-limit relaxation, ordering, flashing or industrial qualification. Preserve the paused historical supervisor; do not create another. Reuse one dashboard surface and the existing task-owned Pup window.
Historical Board34/R10 completion.
Current evidence (v5 side-fan revision)
Latest adopted checkpoint: revisions/compact-r11/kicad/compact-sidefan-v5-native.kicad_pcb (AIFlow board-5). Native DRC: zero errors, warnings and opens; schematic parity passes. V5 passes the fresh 0.1 mm current solve with the unchanged 0.5 A auxiliary allowance. PCB-only Q1 thermal still fails because its external package path is absent; the fresh v5 exploratory package network is not acceptance evidence. All 18 board-level test landings pass and nominal envelope margins pass. The isolated R11 bring-up firmware compiles, with load locked off and explicit full-cooling request; no flash.
The corrected probe checker finds 24 collision episodes and six tether snags when the main cooler/fan reservations are included. Earlier assembled-clearance results are withdrawn: the old checker selected a 4 mm board corner and silently omitted large objects. Owner issue and PR: adom/adom-aiflow-probing#3. The isolated fix also removes a 40 mm moving-head cutoff; shared installed runtimes are unchanged.
A separate J7/TP14 relocation candidate (compact-probe-routed-native.kicad_pcb) passes native DRC and parity, but still has 21 collision episodes and two snags in its cooler replay. It is not adopted. The resulting v5 board moves J7 to (10,4) mm, retains the relocated TP14 and detours PWM locally. The 90-degree side-fan experiment has now been replayed with the actual v5 model: 231.7 seconds, zero collisions and zero snags, with no proposed pads. None of these reservations includes a qualified clamp, duct, ears, sensor or harness.
Six narrated/captioned review scenes are prepared in videos/compact-r11/chapter/storyboard.json. Actual footage includes fan motion, board orbit, the fan Wiki review and cooler-obstacle review. Blank native-editor takes are excluded; no claim of uninterrupted native editing footage. All six scenes are explicitly approved and published as a 96.41-second chapter, with player captions. New assumption-based assembly footage remains separate for review. The 4:09 historical-to-R11 film is now recut and published; player captions were verified on the rendered Wiki page.
Task-local AIFlow runner: tools/aiflow-r11. Source fixes for explicit native read/measurement endpoints are directly published at commits 6ffc663d and 65c0692e; they are tested locally, not a registry/global installed release. Preserve other unsaved editors and the other thread’s probing dashboard.
Latest handoff dependencies
Concrete remaining data, requests and review status. The AIFlow rules-check recording bug is fixed in source commit 542a3c34 and verified on this run without changing the rule file. No thermal or final-delivery gate is marked passed. Supplier requests were sent with authorization on 14 October; technical replies remain pending; the six-scene user review is approved.
Authorized assumption-based prototype continuation — 14 October
User authorized best engineering assumptions for geometry, interface and fan data. Continue prototype work under revisions/compact-r11/assumed-assembly/prototype-contract.json; supplier replies no longer block geometry studies. Keep original qualification gates and failed cases visible. Assumed carrier/duct/clamp geometry and thermal sweep are in progress; neither prototype completion nor industrial qualification is claimed.
Earlier assumption-based checks (superseded by retention and harness revisions): the split-collar carrier assembly cleared the nominal probe replay and the native board-solid intersection check (0 intersections above 0.01 mm³). This is not an assembly-self-intersection, tolerance, strength or thermal qualification. See Q1 thermal sensitivity review.
Retention review iteration — 14 October, 22:30 UTC
The assembly now includes assumed commercial sink ears on 45 mm centers, a 2 mm inward sink relocation to clear the scaffold pin, sink-ear supports and hold-down screws, captive fan nuts, bolted flange returns and sliding duct capture lips. Internal solid overlaps are retained and classified; the latest review has zero unclassified contacts and zero intersections with native board solids. Subsequent probe replay found travel collisions and tether snags, so this is historical evidence, not acceptance of the current model. Fit-part carrier, duct and fan flange export as one connected solid each. Manufactured tolerances, materials, thermal behavior and strain relief remain unqualified. The 4:09 caption-clean R10-to-R11 film was published at source commit80d34ca1 after a task-local DNS workaround; rendered verification follows.
Current mechanical iteration
Cooling shifted 7 mm toward the front; safe travel height is 27 mm. The final carrier includes 10 mm collar bosses and a sensor-wire groove. Internal contact classification has zero unresolved overlaps; the fresh board intersection and MP1-ground probe replay are running. Previous J7 replay had zero head collisions and four fin snags; the earlier sensor-wire diagnosis was incorrect. See assumed-j7-tether-conflict.json. Original thermal qualification remains unmet.
Retained assembly and CLI replay checkpoint
The current assembly has zero native-board solid intersections and zero unclassified internal contacts. Carrier, duct and fan flange each export as one connected solid. Nominal dimensions are83.75×76.25×56.4mm excluding downward pins. The fixture returns to90degrees/J7. The original CLI reported4 tether snags; an isolated, tested encountered-obstacle refinement now reports0 head collisions and0 snags at identical geometry and thresholds. The patch and before/after evidence are on owner issue3; no shared deployment or browser parity is claimed. The browser currently omits this board-obstacle refinement. Margin/coverage completion and the input-bound result are authoritative in assumed-probe-input-review.json.
The new18-second assembly clip is published separately for review. The4:09 main film and its selectable captions are published and visibly verified. Supplier replies and hardware measurements remain qualification dependencies, not blockers to the completed assumption-based studies. Original thermal/finish/delivery gates remain open.
Final nominal CLI checkpoint: all six checks pass (access, stack, compile, collide, margins, coverage). Coverage has20 items:19OK, one near landing atTP14 for L1, zero missing/proposed. Full workcell/browser equivalence remains open and is not marked complete. The prototype ZIP is hash-verified; see its manifest.
Current: direct PCB bracket correction, 15 October
The perimeter carrier is superseded by revisions/compact-r11/assembly-correction/compact-bracket-v6-candidate.kicad_pcb and v6-review.glb. Three M3 mounts attach directly to FR4; the bracket supports the revised ATS sink and fan. Q1 has a specified M3x0.5 custom tap and enlarged driver access. J9/J11/C6/D1 moves require rerouting. Mechanical checks and fastener stack are in DIRECT-BRACKET.md; the current native DRC is not passing. Earlier assembly collision, probe replay, thermal and finished-board evidence do not apply to this revision. No production release or uprating is claimed.
User-prompted probing/sensor review, 15 October
The v6 silk candidate has 115 visible 0.8 mm reference fields and 115 visible 0.3 mm values; native silk/text DRC is clear. Electrical DRC still has 100 violations and 10 opens. The omitted Vishay NTC body is restored against the heatsink underside near Q1; adhesive, full wire route and JST GH termination remain unqualified. AIFlow Probing was restarted against the new anchored assembly: J7 grounding fails with 10 pincer collision episodes and 6 tether snags. MP1 grounding is being evaluated separately; no old v5 acceptance is reused. User prompting and raw recording are documented in docs/user-prompted-review-20261015.md and videos/compact-r11/user-prompted-correction-v6/.
Mounting redesign reopened by user
Replace independent ear/bracket mounting stacks with two coaxial FR4-through mounts at the heatsink ears, using height-setting supports. Remove redundant central mounting point. User identified internal hardware interference; earlier board-only intersection reports do not constitute full-assembly clearance. Do not fabricate the v6 bracket. Sensor selection is now NTCALUG01T103G400A with short leads; termination tolerance and exact routing remain under review.
Current V8: third fan-support bolt, 15 October
User identified the unsupported side of the fan flange. V8 adds H3 at native (160,92) with an M3x16 through-FR4 bolt and a connected height support. The two heatsink ear bolts remain. Full native STEP board collision check finds no unintended support/hardware/component intersections; real openings are verified for H1/H2/H3 and Q1. Sensor mating-envelope fit remains unqualified. Existing Pup viewer now shows V8, and an actual assembly reveal was recorded without burned captions. Fresh patched CLI probing passes head/tether collision and landing margins; no prior revision pass is reused. Native electrical DRC is running; routing and qualification gates remain open. See revisions/compact-r11/fan-support-v8/README.md.
V8 electrical recovery checkpoint
The V8 working candidate now has no native ground-connectivity findings, shorts, clearance or silkscreen violations. Twelve opens remain (USB pair, fused power path, isolated LOAD_POS branch), plus ten dangling tracks and one dangling via. This supersedes earlier V8 counts only; it is not board acceptance. Nine old rectifier thermal vias are being relocated in a separate, unaccepted power-routing experiment; the working candidate retains its checked copper. The 25.1-second mounting/underside review is published.
AIFlow still binds its earlier board-5 snapshot until V8 satisfies the adoption DRC gate. A model-resolution check on that snapshot is historical, not V8 proof. Do not reuse its route/current status as V8 acceptance. V8 needs adoption, model/test-plan/placement revalidation, then all subsequent engineering gates.
V8 adopted electrical checkpoint — 15 October
AIFlow board-6 now contains the native-filled V8 working board. Native DRC has zero violations and zero unconnected items; the 2466-item net-intent map survived native fill/save/reload. Nine rectifier thermal vias were relocated and U10 moved beside USB-C, requiring new current, thermal and assembled-probe checks. fan-support-v8/native-binding.log records byte-matched desktop board and rule sidecars. The fresh model check covers 115 footprints (95 modeled, 20 intentionally model-free), and all 18 board-level test measurements have landing points. These checks do not qualify assembled probe access or thermal performance. Native placement verification is in progress.
The task-local AIFlow binding fix is built and tested but not yet published or installed for other users. The older board-5 model result is superseded. Sensor harness termination, USB signal review, physical cooling/preload validation and final delivery remain open.
Current adopted board-7: mounting clearance
fan-support-v8/mount-clearance-review/v8-mount-clearance-filled.kicad_pcb is adopted, bound to the matching desktop files, and passes native DRC, 2468-item net-intent preservation, 115-part model resolution and native placement verification. H1/H2/H3 now have both-face washer courtyards; F1 moved1mm away and DUT_POS was rerouted. Updated assembly GLB is in the same directory and loaded in the existing Pup viewer. Fresh nominal probing has passed collide/margins; coverage remains running. Do not reuse board-6 solve hashes.
revisions/compact-r11/sensor-ph-review is a separate, unadopted two-pin PH termination candidate. Native schematic parity passes288 pins/112 components. Native DRC cleanup and physical harness modeling remain in progress. Latest accepted run is still board-7.
AIFlow stale remoteBoard fix: owner issue50, direct source74796cfe on immutable0.1.97 basec61d9beb; workspace tests, production check/build, contextual preflight and real positive/negative binding checks passed. Registry/global runtime unchanged. Avoid concurrent state-changing CLI calls on the same run; a stage transition can overwrite a long verification outcome loaded earlier. Re-ran placement during its active visit to retain correct evidence.
Current-density and package-path continuation, 16 October
AIFlow board-11 is current-repair-r5 plus two tiny native-landed5V_AUX links. Pour verification includes H1/H2/H3 washer and Q1 driver keepouts, without replacing zones. Outline rounding found no changes required. Current remains failed; no finish/thermal pass exists.
The rectangular-pad branch-screen defect is fixed in shared source96ef829d009c21097c83486e1ecd25e2f6226eba, ownerissue63, with24 tests passing. Actual R5 DUT_POS now screens pass3.96°C track rise and47.45A/mm² barrel density. Filled-copper Fields remains mandatory. Global installed release availability is separate.
R5 and R4 pass all six stricter nominal probing stages including tether handling and jaw checks. R6 native DRC0/0, but DUT_FUSED74A/mm² still fails. R7 shifts/widens that elbow, native DRC0/0; fresh Fields is running. R6 package cooling is exploratory: Q1+49.55°C still,+12.75°C assumed airflow at5.5W. Still-air35°C budget fails; physical and spatial-heatsink qualification remain open. See q1-package-cooling-review-2026-10-16.md.
A21-second narrated R6 thermal-review clip is rendered remotely on arav-rog, with separate captions. Prior accidental local automatic take was rejected, removed from the clip index, archived remotely and its local raw copies removed. Wrapper now disables automatic focus/capture and raw clip publishing; explicit remote narrated capture remains available.
Correction: stale probing paths discovered, 16 October
R4/R5/R7 recheck scripts hashed their intended new models but the copied probing state still selected the older fan-connector-clearance native board and GLB; the plan.board reference was older still. Those revision-specific probing passes are withdrawn. Current/DRC results are unaffected. R7 is now main AIFlow board-12 and its current gate passes, but its probing acceptance is pending a corrected rerun. The checker now resolves and compares actual state.board/state.glb/plan.board/release SHA before any command, and watches both display and plain models. Shared CLI identity checks and browser obstacle export are being tested. Historical generated reports remain as evidence of the defect, not acceptance.
The R6 thermal video's budget annotation is corrected from the general35°C board budget to the stricter Q1-specific15°C budget. Predicted rises remain49.55°C still and12.75°C moving; neither input nor acceptance limits changed.
2026-10-16 supplier response and corrected thermal study
R7 exact-input probing and the explicit PS2/fan-motion candidate pass six nominal geometry stages. Browser evidence confirms rotor-only motion, pause/seek and shutdown. Linux and native Windows each pass 25 Rust tests; seven JavaScript checks pass. Published fan replay has separate captions and narration. Physical qualification remains false.
ATS's October14 response estimates 9 K/W natural convection for the fine-pitch sink and 4.6 K/W for its coarse-pitch alternative, with catalog heating over the full40x40mm base. Both exceed the existing passive budget under the stated interface assumption. Supplier CAD is not redistributable and stays outside the public repo. Same Sky detailed fan data remains outstanding.
Corrected the older oversized12x18mm Q1 contact by adding a separate assumed8x10mm contact sensitivity at5.5W: case82.44°C with h5 and49.20°C with h50, ambient40°C. Mesh change1→2mm shifts maxima<0.08°C. Neither prescribed h nor contact shape is measured. The narrated17-second layer-reveal clip is on the latest-clips page; raw media stays on arav-rog. Main thermal acceptance stays failed, output locked, original5W cap unchanged. Supplier-informed coupled solve remains separate from accepted spec.
28 October issue repair checkpoint
The active run has adopted board-17 after electronic-load issue #1: a continuous SHUNT_P source pour with 0.25 mm local clearance and one additional 0.6/0.3 mm via at (134.8,86.0) mm. Native DRC has zero errors and zero opens. LOAD_POS sense-only classification is recorded as a spec amendment; original bias assumptions preserved. Current/thermal and downstream export/probe/GLB evidence must be regenerated for this revision. No manufacturing release. See issue repair status.
2026-10-28 issue-repair continuation
- JLCPCB all-copper clearance fix is published and its specific issue closed after native negative-control verification.
- AIFlow 0.2.26 is published and installed; mechanical geometry proof must match the active board and external STEP/request/report hashes. 496 workspace tests pass; nine existing ignored tests remain ignored.
- PCBWay 0.1.1 is now a public MIT wiki app with source, matching Linux asset and verified installation/discovery.
- Mechanical STEP sweep adapter has nine passing geometry/CLI tests; these are synthetic fixtures, not this board's acceptance. Mechanical/Wiring standalone hero publication awaits the batch-style approval answer.
- Active board is board-18. Native DRC is clean with exact project/library context, but full fine-grid current gate remains failed at 72.7733 A/mm². No waiver, reduced current, relaxed threshold or completed-board claim.
- Rounded-pad diagnostic candidates remain unadopted; a wide-source-exit variant is being solved at 0.1 mm. Rerun the full watched solve before any acceptance.
- New retrospective Pup walkthrough recorded on arav-rog with Adom TTS; remote edit/validation in progress. Headless CAD edits were not filmed.
28 October: active board-20 verification
Board-19 full unchanged-spec 0.1 mm solve failed SHUNT_P at 65.887283 A/mm² (limit 60). Board-20 removes only the redundant 2 mm B.Cu source stub, retains the wider pour and parallel feed, and passed native KiCad checks under the existing project context. Full fine-grid solve is running. Required mechanical and wiring reviews remain unresolved; the six current hero conductors pass identity and connected-surface screens only. No manufacturing release or physical qualification.
Board-20 full result: failed at 128.342041 A/mm². Board-21 extends the existing stub instead, from the board-19 baseline; native DRC clean, source-only coarse result 58.515766 A/mm². Full unchanged-spec fine-grid verification running.
28 October — board-22 copper repair accepted by current screening
Board-22 broadens SHUNT_P upper B.Cu pour and passes native DRC, AIFlow current and the full unchanged-spec 0.1 mm current-density solve. SHUNT_P peak57.315754 A/mm²; no limits waived. Board SHA-256: 197e48d41c905773c8c8db092c9db5a255f0b0b919eaf3b645080399c93467d7. Historical board20/21 candidates remain rejected. Mechanical diagnostics bind to board20 and are not board22 acceptance. Thermal cooling path and wiring service evidence remain unresolved; see docs/issue-repairs-20261028/remaining-dependencies.md. No fabrication readiness claimed.
# Completion plan: compact R11
Active run: `aiflow/compact-r11`. User authorized implementation and process recording on 13 October 2026. Board34/R10 remains the archived electrical baseline in `aiflow/run`; its gates do not qualify this revision.
## Required work
- [x] Record scope and preserve baseline identity: `revisions/compact-r11/requirements.json`.
- [ ] Source exact commercial approximately 40 mm tall-fin sink and documented PWM/tach fan, including drawings and connector.
- [x] Design an assumption-based insulated Q1 clamp, sensor retention, carrier and duct; manufactured fit, strength and airflow remain unqualified.
- [x] Pack and route 72 x 72 mm target, large pins at 64 mm spacing, edge USB-C, two-layer 1 oz 3rdPartyFab rules. Retain Q1 and D1.
- [ ] Revalidate netlist, libraries, models, DRC, current and Q1/PCB thermal paths with fan-on/off boundaries.
- [ ] Complete assembled probe simulation including all existing measurements, fan wiring and cooler.
- [x] Compile and bench-simulate output-locked PWM/fault firmware (hardware qualification remains open); retain 5 W cap, output lock and existing temperature protections.
- [x] Write physical cooler/clamp fixture procedure. Physical measurements are pending hardware and cannot be fabricated.
- [x] Publish the prototype board, assumed assembly, R11 specification, review evidence and exact qualification status.
- [x] Publish the approved six-scene chapter in a 4:09 narrated film with selectable captions. New assembly iteration clips remain separate and unapproved.
## Scope boundaries
72 x 72 mm is a fit target, not an accepted layout. No higher wattage rating, temperature-limit relaxation, ordering, flashing or industrial qualification. Preserve the paused historical supervisor; do not create another. Reuse one dashboard surface and the existing task-owned Pup window.
[Historical Board34/R10 completion](completion-plan-history-board34-before-r11.md).
## Current evidence (v5 side-fan revision)
Latest adopted checkpoint: `revisions/compact-r11/kicad/compact-sidefan-v5-native.kicad_pcb` (AIFlow board-5). Native DRC: zero errors, warnings and opens; schematic parity passes. V5 passes the fresh 0.1 mm current solve with the unchanged 0.5 A auxiliary allowance. PCB-only Q1 thermal still fails because its external package path is absent; the fresh v5 exploratory package network is not acceptance evidence. All 18 board-level test landings pass and nominal envelope margins pass. The isolated R11 bring-up firmware compiles, with load locked off and explicit full-cooling request; no flash.
The corrected probe checker finds 24 collision episodes and six tether snags when the main cooler/fan reservations are included. Earlier assembled-clearance results are withdrawn: the old checker selected a 4 mm board corner and silently omitted large objects. Owner issue and PR: adom/adom-aiflow-probing#3. The isolated fix also removes a 40 mm moving-head cutoff; shared installed runtimes are unchanged.
A separate J7/TP14 relocation candidate (`compact-probe-routed-native.kicad_pcb`) passes native DRC and parity, but still has 21 collision episodes and two snags in its cooler replay. It is not adopted. The resulting v5 board moves J7 to (10,4) mm, retains the relocated TP14 and detours PWM locally. The 90-degree side-fan experiment has now been replayed with the actual v5 model: 231.7 seconds, zero collisions and zero snags, with no proposed pads. None of these reservations includes a qualified clamp, duct, ears, sensor or harness.
Six narrated/captioned review scenes are prepared in `videos/compact-r11/chapter/storyboard.json`. Actual footage includes fan motion, board orbit, the fan Wiki review and cooler-obstacle review. Blank native-editor takes are excluded; no claim of uninterrupted native editing footage. All six scenes are explicitly approved and published as a 96.41-second chapter, with player captions. New assumption-based assembly footage remains separate for review. The 4:09 historical-to-R11 film is now recut and published; player captions were verified on the rendered Wiki page.
Task-local AIFlow runner: `tools/aiflow-r11`. Source fixes for explicit native read/measurement endpoints are directly published at commits 6ffc663d and 65c0692e; they are tested locally, not a registry/global installed release. Preserve other unsaved editors and the other thread’s probing dashboard.
## Latest handoff dependencies
[Concrete remaining data, requests and review status](../revisions/compact-r11/evidence/remaining-dependencies.md). The AIFlow rules-check recording bug is fixed in source commit 542a3c34 and verified on this run without changing the rule file. No thermal or final-delivery gate is marked passed. Supplier requests were sent with authorization on 14 October; technical replies remain pending; the six-scene user review is approved.
## Authorized assumption-based prototype continuation — 14 October
User authorized best engineering assumptions for geometry, interface and fan data. Continue prototype work under `revisions/compact-r11/assumed-assembly/prototype-contract.json`; supplier replies no longer block geometry studies. Keep original qualification gates and failed cases visible. Assumed carrier/duct/clamp geometry and thermal sweep are in progress; neither prototype completion nor industrial qualification is claimed.
Earlier assumption-based checks (superseded by retention and harness revisions): the split-collar carrier assembly cleared the nominal probe replay and the native board-solid intersection check (0 intersections above 0.01 mm³). This is not an assembly-self-intersection, tolerance, strength or thermal qualification. See [Q1 thermal sensitivity review](../revisions/compact-r11/assumed-assembly/thermal-review.md).
## Retention review iteration — 14 October, 22:30 UTC
The assembly now includes assumed commercial sink ears on 45 mm centers, a 2 mm inward sink relocation to clear the scaffold pin, sink-ear supports and hold-down screws, captive fan nuts, bolted flange returns and sliding duct capture lips. Internal solid overlaps are retained and classified; the latest review has zero unclassified contacts and zero intersections with native board solids. Subsequent probe replay found travel collisions and tether snags, so this is historical evidence, not acceptance of the current model. Fit-part carrier, duct and fan flange export as one connected solid each. Manufactured tolerances, materials, thermal behavior and strain relief remain unqualified. The 4:09 caption-clean R10-to-R11 film was published at source commit80d34ca1 after a task-local DNS workaround; rendered verification follows.
## Current mechanical iteration
Cooling shifted 7 mm toward the front; safe travel height is 27 mm. The final carrier includes 10 mm collar bosses and a sensor-wire groove. Internal contact classification has zero unresolved overlaps; the fresh board intersection and MP1-ground probe replay are running. Previous J7 replay had zero head collisions and four fin snags; the earlier sensor-wire diagnosis was incorrect. See `assumed-j7-tether-conflict.json`. Original thermal qualification remains unmet.
## Retained assembly and CLI replay checkpoint
The current assembly has zero native-board solid intersections and zero unclassified internal contacts. Carrier, duct and fan flange each export as one connected solid. Nominal dimensions are83.75×76.25×56.4mm excluding downward pins. The fixture returns to90degrees/J7. The original CLI reported4 tether snags; an isolated, tested encountered-obstacle refinement now reports0 head collisions and0 snags at identical geometry and thresholds. The patch and before/after evidence are on owner issue3; no shared deployment or browser parity is claimed. The browser currently omits this board-obstacle refinement. Margin/coverage completion and the input-bound result are authoritative in `assumed-probe-input-review.json`.
The new18-second assembly clip is published separately for review. The4:09 main film and its selectable captions are published and visibly verified. Supplier replies and hardware measurements remain qualification dependencies, not blockers to the completed assumption-based studies. Original thermal/finish/delivery gates remain open.
Final nominal CLI checkpoint: all six checks pass (access, stack, compile, collide, margins, coverage). Coverage has20 items:19OK, one near landing atTP14 for L1, zero missing/proposed. Full workcell/browser equivalence remains open and is not marked complete. The prototype ZIP is hash-verified; see its manifest.
## Current: direct PCB bracket correction, 15 October
The perimeter carrier is superseded by `revisions/compact-r11/assembly-correction/compact-bracket-v6-candidate.kicad_pcb` and `v6-review.glb`. Three M3 mounts attach directly to FR4; the bracket supports the revised ATS sink and fan. Q1 has a specified M3x0.5 custom tap and enlarged driver access. J9/J11/C6/D1 moves require rerouting. Mechanical checks and fastener stack are in `DIRECT-BRACKET.md`; the current native DRC is not passing. Earlier assembly collision, probe replay, thermal and finished-board evidence do not apply to this revision. No production release or uprating is claimed.
## User-prompted probing/sensor review, 15 October
The v6 silk candidate has 115 visible 0.8 mm reference fields and 115 visible 0.3 mm values; native silk/text DRC is clear. Electrical DRC still has 100 violations and 10 opens. The omitted Vishay NTC body is restored against the heatsink underside near Q1; adhesive, full wire route and JST GH termination remain unqualified. AIFlow Probing was restarted against the new anchored assembly: J7 grounding fails with 10 pincer collision episodes and 6 tether snags. MP1 grounding is being evaluated separately; no old v5 acceptance is reused. User prompting and raw recording are documented in docs/user-prompted-review-20261015.md and videos/compact-r11/user-prompted-correction-v6/.
## Mounting redesign reopened by user
Replace independent ear/bracket mounting stacks with two coaxial FR4-through mounts at the heatsink ears, using height-setting supports. Remove redundant central mounting point. User identified internal hardware interference; earlier board-only intersection reports do not constitute full-assembly clearance. Do not fabricate the v6 bracket. Sensor selection is now NTCALUG01T103G400A with short leads; termination tolerance and exact routing remain under review.
## Current V8: third fan-support bolt, 15 October
User identified the unsupported side of the fan flange. V8 adds H3 at native (160,92) with an M3x16 through-FR4 bolt and a connected height support. The two heatsink ear bolts remain. Full native STEP board collision check finds no unintended support/hardware/component intersections; real openings are verified for H1/H2/H3 and Q1. Sensor mating-envelope fit remains unqualified. Existing Pup viewer now shows V8, and an actual assembly reveal was recorded without burned captions. Fresh patched CLI probing passes head/tether collision and landing margins; no prior revision pass is reused. Native electrical DRC is running; routing and qualification gates remain open. See revisions/compact-r11/fan-support-v8/README.md.
## V8 electrical recovery checkpoint
The V8 working candidate now has no native ground-connectivity findings, shorts, clearance or silkscreen violations. Twelve opens remain (USB pair, fused power path, isolated LOAD_POS branch), plus ten dangling tracks and one dangling via. This supersedes earlier V8 counts only; it is not board acceptance. Nine old rectifier thermal vias are being relocated in a separate, unaccepted power-routing experiment; the working candidate retains its checked copper. The 25.1-second mounting/underside review is published.
AIFlow still binds its earlier board-5 snapshot until V8 satisfies the adoption DRC gate. A model-resolution check on that snapshot is historical, not V8 proof. Do not reuse its route/current status as V8 acceptance. V8 needs adoption, model/test-plan/placement revalidation, then all subsequent engineering gates.
## V8 adopted electrical checkpoint — 15 October
AIFlow board-6 now contains the native-filled V8 working board. Native DRC has zero violations and zero unconnected items; the 2466-item net-intent map survived native fill/save/reload. Nine rectifier thermal vias were relocated and U10 moved beside USB-C, requiring new current, thermal and assembled-probe checks. `fan-support-v8/native-binding.log` records byte-matched desktop board and rule sidecars. The fresh model check covers 115 footprints (95 modeled, 20 intentionally model-free), and all 18 board-level test measurements have landing points. These checks do not qualify assembled probe access or thermal performance. Native placement verification is in progress.
The task-local AIFlow binding fix is built and tested but not yet published or installed for other users. The older board-5 model result is superseded. Sensor harness termination, USB signal review, physical cooling/preload validation and final delivery remain open.
## Current adopted board-7: mounting clearance
`fan-support-v8/mount-clearance-review/v8-mount-clearance-filled.kicad_pcb` is adopted, bound to the matching desktop files, and passes native DRC, 2468-item net-intent preservation, 115-part model resolution and native placement verification. H1/H2/H3 now have both-face washer courtyards; F1 moved1mm away and DUT_POS was rerouted. Updated assembly GLB is in the same directory and loaded in the existing Pup viewer. Fresh nominal probing has passed collide/margins; coverage remains running. Do not reuse board-6 solve hashes.
`revisions/compact-r11/sensor-ph-review` is a separate, unadopted two-pin PH termination candidate. Native schematic parity passes288 pins/112 components. Native DRC cleanup and physical harness modeling remain in progress. Latest accepted run is still board-7.
AIFlow stale remoteBoard fix: owner issue50, direct source74796cfe on immutable0.1.97 basec61d9beb; workspace tests, production check/build, contextual preflight and real positive/negative binding checks passed. Registry/global runtime unchanged. Avoid concurrent state-changing CLI calls on the same run; a stage transition can overwrite a long verification outcome loaded earlier. Re-ran placement during its active visit to retain correct evidence.
## Current-density and package-path continuation, 16 October
AIFlow board-11 is current-repair-r5 plus two tiny native-landed5V_AUX links. Pour verification includes H1/H2/H3 washer and Q1 driver keepouts, without replacing zones. Outline rounding found no changes required. Current remains failed; no finish/thermal pass exists.
The rectangular-pad branch-screen defect is fixed in shared source96ef829d009c21097c83486e1ecd25e2f6226eba, ownerissue63, with24 tests passing. Actual R5 DUT_POS now screens pass3.96°C track rise and47.45A/mm² barrel density. Filled-copper Fields remains mandatory. Global installed release availability is separate.
R5 and R4 pass all six stricter nominal probing stages including tether handling and jaw checks. R6 native DRC0/0, but DUT_FUSED74A/mm² still fails. R7 shifts/widens that elbow, native DRC0/0; fresh Fields is running. R6 package cooling is exploratory: Q1+49.55°C still,+12.75°C assumed airflow at5.5W. Still-air35°C budget fails; physical and spatial-heatsink qualification remain open. See q1-package-cooling-review-2026-10-16.md.
A21-second narrated R6 thermal-review clip is rendered remotely on arav-rog, with separate captions. Prior accidental local automatic take was rejected, removed from the clip index, archived remotely and its local raw copies removed. Wrapper now disables automatic focus/capture and raw clip publishing; explicit remote narrated capture remains available.
## Correction: stale probing paths discovered, 16 October
R4/R5/R7 recheck scripts hashed their intended new models but the copied probing state still selected the older fan-connector-clearance native board and GLB; the plan.board reference was older still. Those revision-specific probing passes are withdrawn. Current/DRC results are unaffected. R7 is now main AIFlow board-12 and its current gate passes, but its probing acceptance is pending a corrected rerun. The checker now resolves and compares actual state.board/state.glb/plan.board/release SHA before any command, and watches both display and plain models. Shared CLI identity checks and browser obstacle export are being tested. Historical generated reports remain as evidence of the defect, not acceptance.
The R6 thermal video's budget annotation is corrected from the general35°C board budget to the stricter Q1-specific15°C budget. Predicted rises remain49.55°C still and12.75°C moving; neither input nor acceptance limits changed.
## 2026-10-16 supplier response and corrected thermal study
R7 exact-input probing and the explicit PS2/fan-motion candidate pass six nominal geometry stages. Browser evidence confirms rotor-only motion, pause/seek and shutdown. Linux and native Windows each pass 25 Rust tests; seven JavaScript checks pass. Published fan replay has separate captions and narration. Physical qualification remains false.
ATS's October14 response estimates 9 K/W natural convection for the fine-pitch sink and 4.6 K/W for its coarse-pitch alternative, with catalog heating over the full40x40mm base. Both exceed the existing passive budget under the stated interface assumption. Supplier CAD is not redistributable and stays outside the public repo. Same Sky detailed fan data remains outstanding.
Corrected the older oversized12x18mm Q1 contact by adding a separate assumed8x10mm contact sensitivity at5.5W: case82.44°C with h5 and49.20°C with h50, ambient40°C. Mesh change1→2mm shifts maxima<0.08°C. Neither prescribed h nor contact shape is measured. The narrated17-second layer-reveal clip is on the latest-clips page; raw media stays on arav-rog. Main thermal acceptance stays failed, output locked, original5W cap unchanged. Supplier-informed coupled solve remains separate from accepted spec.
## 28 October issue repair checkpoint
The active run has adopted board-17 after electronic-load issue #1: a continuous SHUNT_P source pour with 0.25 mm local clearance and one additional 0.6/0.3 mm via at (134.8,86.0) mm. Native DRC has zero errors and zero opens. LOAD_POS sense-only classification is recorded as a spec amendment; original bias assumptions preserved. Current/thermal and downstream export/probe/GLB evidence must be regenerated for this revision. No manufacturing release. See [issue repair status](issue-repairs-20261028/README.md).
## 2026-10-28 issue-repair continuation
- JLCPCB all-copper clearance fix is published and its specific issue closed after native negative-control verification.
- AIFlow 0.2.26 is published and installed; mechanical geometry proof must match the active board and external STEP/request/report hashes. 496 workspace tests pass; nine existing ignored tests remain ignored.
- PCBWay 0.1.1 is now a public MIT wiki app with source, matching Linux asset and verified installation/discovery.
- Mechanical STEP sweep adapter has nine passing geometry/CLI tests; these are synthetic fixtures, not this board's acceptance. Mechanical/Wiring standalone hero publication awaits the batch-style approval answer.
- Active board is board-18. Native DRC is clean with exact project/library context, but full fine-grid current gate remains failed at 72.7733 A/mm². No waiver, reduced current, relaxed threshold or completed-board claim.
- Rounded-pad diagnostic candidates remain unadopted; a wide-source-exit variant is being solved at 0.1 mm. Rerun the full watched solve before any acceptance.
- New retrospective Pup walkthrough recorded on arav-rog with Adom TTS; remote edit/validation in progress. Headless CAD edits were not filmed.
### 28 October: active board-20 verification
Board-19 full unchanged-spec 0.1 mm solve failed SHUNT_P at 65.887283 A/mm² (limit 60). Board-20 removes only the redundant 2 mm B.Cu source stub, retains the wider pour and parallel feed, and passed native KiCad checks under the existing project context. Full fine-grid solve is running. Required mechanical and wiring reviews remain unresolved; the six current hero conductors pass identity and connected-surface screens only. No manufacturing release or physical qualification.
Board-20 full result: failed at 128.342041 A/mm². Board-21 extends the existing stub instead, from the board-19 baseline; native DRC clean, source-only coarse result 58.515766 A/mm². Full unchanged-spec fine-grid verification running.
## 28 October — board-22 copper repair accepted by current screening
Board-22 broadens SHUNT_P upper B.Cu pour and passes native DRC, AIFlow current and the full unchanged-spec 0.1 mm current-density solve. SHUNT_P peak57.315754 A/mm²; no limits waived. Board SHA-256: `197e48d41c905773c8c8db092c9db5a255f0b0b919eaf3b645080399c93467d7`. Historical board20/21 candidates remain rejected. Mechanical diagnostics bind to board20 and are not board22 acceptance. Thermal cooling path and wiring service evidence remain unresolved; see docs/issue-repairs-20261028/remaining-dependencies.md. No fabrication readiness claimed.