Power-track widening — 2026-10-08
Twelve 1.2 mm power-track segments were widened to 1.5 or 2.0 mm in native KiCad after isolated candidate checks. Blanket widening caused clearance/short failures and was rejected. No fabrication rule was relaxed. The saved board has zero native DRC findings and zero open connections under the recorded check settings; its 1,674 segments and 253 vias match the accepted candidate geometry.
Electrical screen
A project-only Fields diagnostic applies 3 A to explicit component terminals, with 35 µm copper and a 0.2 mm mesh. All main return is assumed to exit J2.1. The same source and terminal assumptions were used for both candidates.
| Net | Peak current density before / after, A/mm² | Copper loss before / after, W |
|---|---|---|
| DUT_POS | 85.6 / 65.1 | 0.036 / 0.024 |
| DUT_FUSED | 105.8 / 95.4 | 0.042 / 0.040 |
| LOAD_POS | 95.6 / 89.7 | 0.081 / 0.079 |
| SHUNT_P | 111.5 / 111.5 | 0.047 / 0.045 |
| GND | 24.8 / 24.8 | 0.027 / 0.027 |
Total modeled copper loss falls from approximately 0.233 W to 0.215 W, about 8%. Four power-neck screening flags remain, including an unchanged SHUNT_P peak. This does not establish a 3 A rating. The experimental solver fixes are proposed in Fields PR 5, with 21 tests passing; the shared installation is unchanged.
The cooling assembly, MOSFET SOA, USB layout and hardware calibration remain unresolved. Bring-up policy remains 5 W; no hardware has been qualified or released for fabrication.
Evidence and recording
- Saved native DRC, including ignored-check list.
- Saved geometry and hashes.
- Before electrical screen and wider candidate screen.
- Candidate change list.
The actual edits were recorded in a 48.93-second raw take. Overview-scale changes are too subtle to approve it as a construction highlight; it is retained locally with the recorder timing warning. The project now has 28 raw takes and ten reviewed excerpts. The final narrated film remains unfinished.
# Power-track widening — 2026-10-08
Twelve 1.2 mm power-track segments were widened to 1.5 or 2.0 mm in native KiCad after isolated candidate checks. Blanket widening caused clearance/short failures and was rejected. No fabrication rule was relaxed. The saved board has zero native DRC findings and zero open connections under the recorded check settings; its 1,674 segments and 253 vias match the accepted candidate geometry.
## Electrical screen
A project-only Fields diagnostic applies 3 A to explicit component terminals, with 35 µm copper and a 0.2 mm mesh. All main return is assumed to exit J2.1. The same source and terminal assumptions were used for both candidates.
| Net | Peak current density before / after, A/mm² | Copper loss before / after, W |
|---|---:|---:|
| DUT_POS | 85.6 / 65.1 | 0.036 / 0.024 |
| DUT_FUSED | 105.8 / 95.4 | 0.042 / 0.040 |
| LOAD_POS | 95.6 / 89.7 | 0.081 / 0.079 |
| SHUNT_P | 111.5 / 111.5 | 0.047 / 0.045 |
| GND | 24.8 / 24.8 | 0.027 / 0.027 |
Total modeled copper loss falls from approximately 0.233 W to 0.215 W, about 8%. Four power-neck screening flags remain, including an unchanged SHUNT_P peak. This does not establish a 3 A rating. The experimental solver fixes are proposed in [Fields PR 5](https://wiki.adom.inc/adom/adom-fields/prs/5), with 21 tests passing; the shared installation is unchanged.
The cooling assembly, MOSFET SOA, USB layout and hardware calibration remain unresolved. Bring-up policy remains 5 W; no hardware has been qualified or released for fabrication.
## Evidence and recording
- [Saved native DRC](../design/power-width-saved-drc.json), including ignored-check list.
- [Saved geometry and hashes](../design/power-width-saved-audit.json).
- [Before electrical screen](../design/power-paths-explicit-0p2.json) and [wider candidate screen](../design/power-paths-wider-0p2.json).
- [Candidate change list](../checkpoints/power-width-review/v3/selective-review.json).
The actual edits were recorded in a 48.93-second raw take. Overview-scale changes are too subtle to approve it as a construction highlight; it is retained locally with the recorder timing warning. The project now has 28 raw takes and ten reviewed excerpts. The final narrated film remains unfinished.