John Lauer Widen twelve power segments and publish saved native checks and electrical comparison 3938033

Power-track widening — 2026-10-08

Twelve 1.2 mm power-track segments were widened to 1.5 or 2.0 mm in native KiCad after isolated candidate checks. Blanket widening caused clearance/short failures and was rejected. No fabrication rule was relaxed. The saved board has zero native DRC findings and zero open connections under the recorded check settings; its 1,674 segments and 253 vias match the accepted candidate geometry.

Electrical screen

A project-only Fields diagnostic applies 3 A to explicit component terminals, with 35 µm copper and a 0.2 mm mesh. All main return is assumed to exit J2.1. The same source and terminal assumptions were used for both candidates.

Net Peak current density before / after, A/mm² Copper loss before / after, W
DUT_POS 85.6 / 65.1 0.036 / 0.024
DUT_FUSED 105.8 / 95.4 0.042 / 0.040
LOAD_POS 95.6 / 89.7 0.081 / 0.079
SHUNT_P 111.5 / 111.5 0.047 / 0.045
GND 24.8 / 24.8 0.027 / 0.027

Total modeled copper loss falls from approximately 0.233 W to 0.215 W, about 8%. Four power-neck screening flags remain, including an unchanged SHUNT_P peak. This does not establish a 3 A rating. The experimental solver fixes are proposed in Fields PR 5, with 21 tests passing; the shared installation is unchanged.

The cooling assembly, MOSFET SOA, USB layout and hardware calibration remain unresolved. Bring-up policy remains 5 W; no hardware has been qualified or released for fabrication.

Evidence and recording

The actual edits were recorded in a 48.93-second raw take. Overview-scale changes are too subtle to approve it as a construction highlight; it is retained locally with the recorder timing warning. The project now has 28 raw takes and ten reviewed excerpts. The final narrated film remains unfinished.