← Commit history

Verify AIFlow 0.1.87 delivery and preserve active thermal completion requirements

John Lauer ·17ee21b248 ·15d ago ·parent 8c1d740
3 files changed +31−2
design/aiflow-artifact-fix-review.jsonadded+29
@@ -0,0 +1,29 @@+{+  "status": "published-and-installed",+  "base": "6f1e2b631890d225c43019fdf9ca10e2fa2b51f3",+  "version": "0.1.87",+  "workspaceTestsPassed": 150,+  "productionCheck": "pass",+  "preflight": "pass; focused diff reviewed",+  "rootCause": "external artifacts copied by basename, copy errors ignored; in-run sources remained mutable references",+  "change": "verified content-addressed copies and ledger SHA-256/sourceFile; existing files not overwritten",+  "publication": "source, registry, standalone and installed copy verified",+  "nativeBoardChanged": false,+  "remaining": [],+  "sourceCommit": "40cd80ecb12f80540d98b8e1732a1d635276d9c0",+  "sourceReadback": "nine changed files match",+  "registrySha256": "4f5e4e20d7f4c3fe19e42f1541aa7ac2ea81a552155c2311db346d74320ada0f",+  "binarySha256": "b4a2a13bbf2e527e1fc56061a40fc11d2961bc892be69b0b3c8028c02c89964c",+  "standaloneMatches": true,+  "installedMatches": true,+  "cliHelp": "complete help output unchanged",+  "cliWorkflow": "new regression fails on 0.1.86 and passes on 0.1.87",+  "otherChecks": [+    "component workflow",+    "dashboard lifecycle",+    "continuation",+    "widget workflow",+    "silkscreen layout"+  ],+  "wikiScreenshot": "/home/adom/project/screenshots/adom-bridge/window/2026-10-10T18-19-39.506.png"+}
docs/completion-plan.md+1−1
@@ -22,7 +22,7 @@ Continue the custom electronic load through AIFlow, firmware/control-panel and m  ## Tool and delivery boundaries -AIFlow 0.1.86 source, registry and installed executable were verified separately; direct updates are authorized but must use fresh upstream state. Fields owner PRs remain review-only; never merge them or replace shared Fields 8875. The isolated solver is in `fields-package-load-target/release/adom-fields`.+AIFlow 0.1.87 source, registry and installed executable were verified separately; direct updates are authorized but must use fresh upstream state. Fields owner PRs remain review-only; never merge them or replace shared Fields 8875. The isolated solver is in `fields-package-load-target/release/adom-fields`.  Keep the timeline visible at `http://8893.localhost:63548/`. Wrap real external engineering in `adom-aiflow exec`; no idle heartbeat. Register unique artifact filenames to avoid the known basename collision. Keep public fabrication terminology to 3rdPartyFab. Preserve other threads, pinned bridges and user browser tabs. 
docs/status.md+1−1
@@ -10,7 +10,7 @@ The schematic/netlist/BOM and native models now include SBR10U45SP5-13. The v85  Thermal acceptance is still failed. The board-only model injects 5.5 W through Q1’s PCB terminal region and lacks its external case-to-heatsink path; its extreme temperatures are not a prediction of an assembled cooled unit. The actual interface, supported sink/fan mounting, duct pressure/flow and fault behavior require completion. The stock sink envelope clears all 91 fitted models and probe approaches, but this excludes mating connectors and hardware. [Package sensitivity](package-cooling-review.md) · [Fan airflow review](fan-airflow-review.md). -AIFlow 0.1.86 is published and installed with 147 tests passing, verified live presentation refresh and read-only existing-pour verification. Fields PR10 remains a separate owner-review change, and the shared runtime is not replaced. There are 90 raw takes, including static/rejected footage, 34 reviewed excerpts and 30 storyboard clips. The latest excerpt inspects a nominal insulating fastener; thermal qualification remains open. The final narrated 4–5 minute film remains unfinished.+AIFlow 0.1.87 is published and installed with 150 tests passing, verified live presentation refresh and read-only existing-pour verification. Fields PR10 remains a separate owner-review change, and the shared runtime is not replaced. There are 90 raw takes, including static/rejected footage, 34 reviewed excerpts and 30 storyboard clips. The latest excerpt inspects a nominal insulating fastener; thermal qualification remains open. The final narrated 4–5 minute film remains unfinished.  Next: complete the package/interface/duct cooling design and represent its supported operating/fault cases; then same-input thermal acceptance, Fields/pour walkthroughs, current-board silkscreen/3D review, prototype manufacturing outputs and final video. Physical calibration, safety tests and industrial qualification remain separate from digital design acceptance. No fabrication release, order or flash has occurred.